Ops/Comm Scheduling meeting¶
Location : CR21 in R1 @ 15:30 pm on November 22nd
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
- MOM report
- Started 'running' on Friday evening with a 24-hour shift.
- ISIS very unstable. Switched on Sunday to TS2 timing.
- Conventional water issues, now resolved.
- Superconducting magnets regularly monitored. Very stable.
- Run plan:
- Have data for 2 of the settings.
- Prepared a third beam setting for recording over night
- More beam tuning tomorrow.
- Loss of shift cover for SS monitoring at 4pm tomorrow.
- Ramp magnets down at 2pm (Agreed).
- data summary as of 3.30 pm yesterday - Rogers gives apologies
- SS Magnet status
- Magnet alarms need adjusting, to reflect running performance.
- Feedback from joseph to pierrick regarding operation by non-ss personel.
- Hydrogen status
- Cooling, Absorber at 46K. 2nd stage ~26K.
- Monitor overnight and determine coldest temperature. Then will try using heater.
- Conventional magnet water flow issue
- Removed PLC from both contentional water pumps.
- Pump set to deliver constrant pressure from configuration app.
- Wednesday maintenance plans
- No plans.
- Run plans for the next week (discuss)
- Wednesday 23rd : ramp down the SS magnets / maintenance
- Thursday : Shift training + 1 shift - straight track running
- Friday - Sunday : 1 shift per day - straight track running
- Monday 28th : ramp up SS magnets
- Missing shifts
- Still have some missing shift slots for minimal running
- Friday 25th : BLOC
- Dec 3 : Overnight monitoring shift (00:00 - 08:00)
- Still have some missing shift slots for minimal running
- AOB
Updated by Overton, Edward almost 7 years ago ยท 11 revisions