Actions
Ops/Comm Scheduling meeting¶
Location : CR21 in R1 @ 15:30 pm on November 1st
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Hall work¶
- DC report
- Magnet status
- Hydrogen status
- Wednesday maintenance jobs 26th October
- Shutdown activities : 28 October - 15 November (Colin)
Operations¶
- MOM report and run plan to end of user cycle
- Data-taking Summary to date: attachment:MiloradForKan.ods
Overall run time | 51 hours | |||||||||
Task | Description | Momentum | Triggers taken | SSU (ECE) | SSU M1/M2 | FC | SSD (ECE) | SSD M1/M2 | Beamline tag | Cooling channel tag |
2 | Scattering | 140 | 675k at TOF2 | Y | Y/Y | Solenoid | Y | N/N | 3-140+M3-Test2 | CCramp-6.1.4-NoTrims |
3 | Scattering | 170 | 537k at TOF2 | Y | Y/Y | Solenoid | Y | N/N | 3-170+M3-Test1 | CCramp-6.1.4-NoTrims |
4 | Scattering | 200 | 508k at TOF2 | Y | Y/Y | Solenoid | Y | N/N | 3-200+M3-Test1 | CCramp-6.1.4-NoTrims |
5 | Scattering | 240 | 517k at TOF2 | Y | Y/Y | Solenoid | Y | N/N | 3-240+M3-Test1 | CCramp-6.1.4-NoTrims |
- Beam tuning
- Runs with different diffuser settings
- Physics summary (C. Rogers)
- Scheduling of the expert led run for next user cycle
Updated by Boyd, Steven over 6 years ago ยท 5 revisions