Boyd, Steven, 06 September 2016 14:58

1 1 Boyd, Steven
h1. Ops/Comm Scheduling meeting
2
3
Location : CR21 in R1 @ 15:30 pm on September 6th
4
5
Phone access :  ReadyTalk number 
6
US 866-740-1260
7
UK 0800-496-0576
8
Swiss 0800-70-53-51
9
Italy 800182592
10
Access Code: 2155402
11
12 8 Boyd, Steven
h2. Hall work
13
14 1 Boyd, Steven
* DC report
15 3 Blackmore, Victoria
** SSU/FC ramp went well
16
** SSD diode test report
17
** DS compressor progress
18
** Aircon in RR2 now keeping rack temperatures beneath 30C.
19
** Water to conventional magnets...
20
** MICE hall tour for FFAG workshop, Wednesday 7th September
21
** Other:
22
*** Need to get downstream tracker cooling ASAP
23
*** Cover for SS QP cables in RR2
24
*** UPS to be installed in RR!
25
26 1 Boyd, Steven
* Plans for the following week
27 2 Boyd, Steven
* [[StepIV Shutdown tasks|http://micewww.pp.rl.ac.uk/projects/operations/wiki/_StepIV_Shutdown_Summer_]]
28 6 Boyd, Steven
29 7 Boyd, Steven
h2. Operations and data-taking
30
31 6 Boyd, Steven
* Data-taking
32 5 Boyd, Steven
** Start of data-taking has been pushed back to 18 or 19 September (from the 13th). 
33
** Will need to make a decision once the DS work has been carried out on how/when we run.
34 4 Boyd, Steven
** We do need an expert run : this has been discussed and planned for Sept 12 (pulsers) and Sept 13 (beam). 
35 1 Boyd, Steven
** We will need to do beam tuning as usual. 
36 6 Boyd, Steven
* Maintenance plans
37
** Should decide on a regular maintenance slot (for e.g. checking temporary neutron monitor)
38
*** Wednesday morning?
39 1 Boyd, Steven
* AOB 
40
41
* DONM : 13th September in CR12