Actions
Ops/Comm Scheduling meeting¶
Location : CR22 in R1 @ 15:30 pm on Tuesday 7th
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
- Generate appropriate table to store absorber pressure and material information (Janusz) : Janusz coming on Wed. Stands
- DS readback current requires calibration (DL) : Asked Daresbury when they can schedule it. Stands
- John G to think about a shielding solution for the Hall probe connectors
- SSH lockout procedure documentation (Paolo) and details of implementation (Steve)
- Go over FC and DS alarm handler spreadsheets (Pierrick,Mark,John C)
- Keep on top of SS documentation (Josef,All)
- Install FC monitoring in ISIS MCR (Pierrick,Paolo)
- Implement a search function for the CDB (Someone)
*DC report
*Work plan for the next week: 2016-06-20-Workplan.pdf
Ongoing work
- SS QD/QP commissioning
- Electrical work (flagging DS Calibration)
- Water system work
- FC cooldown and testing
- Planning for July running
- Reminder
- Hall locked on afternoon of Friday 24th
- Monday 27th - Startup with pulsers
- Tuesday 28th - Startup with beam ; 11 am beam tune with ISIS
- Shifts and shift takeup : https://cheese.mice.rl.ac.uk/web/calendar.cgi
- Training plan : http://micewww.pp.rl.ac.uk/projects/operations/wiki/TrainingPlan201602
- New elements
- Whatever is needed for the SS and FC
- Alarm Handler
- New elements
- CDB : do we have all necessary information in the CDB
- Get Target Depth, Target Delay, Total Beam Loss to read out (currently 0 or blank)
- Solenoid currents
- Solenoid polarity
- Focus coil current
- Focus coil polarity
- Absorber material
- Absorber pressure (if necessary)
- Tracker gas and pressure
- CDB Search tool?
- Progress on SS procedure documentation
- Formal freeze of online software : Monday 27th
- Reminder
- Vote for your favourite MICE painting!
- Design 1 : AlQassab-Pascha-1.jpg
- Design 2 : Crowher_Joe.jpg
- AOB
- DONM : 21/6/2016
Updated by Boyd, Steven almost 7 years ago ยท 23 revisions