20160503 » History » Version 9
Boyd, Steven, 03 May 2016 15:25
1 | 1 | Boyd, Steven | h1. Ops/Comm Scheduling meeting |
---|---|---|---|
2 | |||
3 | Location : CR11 in R3 @ 15:30 pm on Tuesday 3rd |
||
4 | |||
5 | Phone access : ReadyTalk number |
||
6 | US 866-740-1260 |
||
7 | UK 0800-496-0576 |
||
8 | Swiss 0800-70-53-51 |
||
9 | Italy 800182592 |
||
10 | Access Code: 2155402 |
||
11 | |||
12 | h1. Agenda |
||
13 | |||
14 | * *Actions from last meeting* |
||
15 | ** Generate appropriate table to store absorber pressure and material information (Janusz) : (almost done) |
||
16 | ** DS readback current requires calibration (DL) : stands until close to powerup |
||
17 | ** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands |
||
18 | ** Move the tracker CAENbus module higher up the chain (Craig) |
||
19 | ** Get an estimate for how long it takes to wire in the chiller in (Andy) |
||
20 | |||
21 | * DC report |
||
22 | 5 | Boyd, Steven | * Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx |
23 | 9 | Boyd, Steven | * QP/QD work : |
24 | 1 | Boyd, Steven | * Water system work plan |
25 | * Bellows installation and FC cooldown |
||
26 | * Tracker hall probe installation |
||
27 | * AOB |
||
28 | 4 | Karadzhov, Yordan | ** Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle: |
29 | http://doodle.com/poll/wnkk4aevq938keb8yinf8gkm/admin#table |
||