Ops/Comm Scheduling meeting¶
Location : CR11 in R3 @ 15:30 pm on Tuesday 3rd
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Agenda¶
- Actions from last meeting
- Generate appropriate table to store absorber pressure and material information (Janusz) : (almost done)
- DS readback current requires calibration (DL) : stands until close to powerup
- Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands
- Move the tracker CAENbus module higher up the chain (Craig)
- Get an estimate for how long it takes to wire in the chiller in (Andy)
- DC report
- Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx
- QP/QD work
- Water system work plan
- Bellows installation and FC cooldown
- Tracker hall probe installation
- AOB
- Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle:
http://doodle.com/poll/wnkk4aevq938keb8yinf8gkm/admin#table
- Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle:
- DONM : 10/3/2016