20160503 » History » Version 17
Hodgson, Paul, 04 May 2016 10:05
1 | 1 | Boyd, Steven | h1. Ops/Comm Scheduling meeting |
---|---|---|---|
2 | |||
3 | Location : CR11 in R3 @ 15:30 pm on Tuesday 3rd |
||
4 | |||
5 | Phone access : ReadyTalk number |
||
6 | US 866-740-1260 |
||
7 | UK 0800-496-0576 |
||
8 | Swiss 0800-70-53-51 |
||
9 | Italy 800182592 |
||
10 | Access Code: 2155402 |
||
11 | |||
12 | h1. Agenda |
||
13 | |||
14 | * *Actions from last meeting* |
||
15 | ** Generate appropriate table to store absorber pressure and material information (Janusz) : (almost done) |
||
16 | ** DS readback current requires calibration (DL) : stands until close to powerup |
||
17 | ** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands |
||
18 | ** Move the tracker CAENbus module higher up the chain (Craig) |
||
19 | ** Get an estimate for how long it takes to wire in the chiller in (Andy) |
||
20 | |||
21 | * DC report |
||
22 | 16 | Hodgson, Paul | * Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6185/2016-05-03-MICE-Hall-Plan.xlsx |
23 | 10 | Boyd, Steven | * QP/QD work : http://micewww.pp.rl.ac.uk/attachments/6181/MICE_Electrical_Work_List_25APR16.docx |
24 | 1 | Boyd, Steven | * Water system work plan |
25 | * Bellows installation and FC cooldown |
||
26 | * Tracker hall probe installation |
||
27 | * AOB |
||
28 | 4 | Karadzhov, Yordan | ** Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle: |
29 | 11 | Karadzhov, Yordan | http://doodle.com/poll/wnkk4aevq938keb8 |
30 | 1 | Boyd, Steven | |
31 | * DONM : 10/3/2016 |
||
32 | 14 | Boyd, Steven | |
33 | 12 | Boyd, Steven | h1. Minutes |
34 | 1 | Boyd, Steven | |
35 | 14 | Boyd, Steven | * *Present* : Yordan, Paul H, Paul S, Mike C, Vicky B, Josef F, Colin W, Andy N, Craig M, Steve B, Pierrick H, Ken L |
36 | 12 | Boyd, Steven | |
37 | * *Actions from last meeting* |
||
38 | 13 | Boyd, Steven | ** Generate appropriate table to store absorber pressure and material information (Janusz) : (almost done) |
39 | ** DS readback current requires calibration (DL) : stands until close to powerup |
||
40 | ** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands |
||
41 | ** Get an estimate for how long it takes to wire in the chiller in (Andy) : Done - about 3-4 days. |
||
42 | 12 | Boyd, Steven | |
43 | * DC report |
||
44 | ** Focus coil won't go back in since the bellows have been switched around and now the screw hole tolerances no longer match. |
||
45 | ** When John gets back from holiday the FC will be pulled out and the bellows swapped |
||
46 | ** Daresbury work went well. An ongoing work plan is shown below |
||
47 | ** US team came out with a program of work, some of which can be done but because the racks are not fully commissioned the |
||
48 | full program of work can't be completed. |
||
49 | ** This week HPC have started to work on the compressor for the DS. They are concerned about the temperature of the air end - it's |
||
50 | 1 | Boyd, Steven | too hot to touch. They plan to replace this in August. Colin:Can we just buy a new one rather than replace in August? Mike: What we |
51 | get is effectively new but we should put an order in. Colin:we should do a comprehensive job on fixing the compressor so need to |
||
52 | 13 | Boyd, Steven | understand this issue. |
53 | *** *Action Item*: Vicky will investigate the state of the refurbished air end to see what we get for our money. |
||
54 | 12 | Boyd, Steven | ** Daresbury will allow the US to run into a short this week. |
55 | ** Alan B : the 20 psi main relief valve for SSU needs replacing. Alan has a replacement but it needs installation. This can happen |
||
56 | 1 | Boyd, Steven | when John is back next week. |
57 | 17 | Hodgson, Paul | * Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6185/2016-05-02-Workplan.pdf |
58 | 1 | Boyd, Steven | ** Henry: Water plan goes into period when the DSA is closed. If we turn the water back on we may be in a situation where the |
59 | water pipes to the conventional magnets could blow. If the DSA is closed we can't get to it. Colin: Good point. Henry: We also |
||
60 | 13 | Boyd, Steven | need the full ISIS running schedule spreadsheet. Colin:I've got something - I'll send it to you. |
61 | ** *Action Item*: Colin will put the ISIS dates for run-ups and machine work into his schedules to better reflect available access time. |
||
62 | 12 | Boyd, Steven | * QP/QD work |
63 | 13 | Boyd, Steven | ** Discussed during the DC report |
64 | 1 | Boyd, Steven | * Water system work plan : Colin:There is no day-by-day plan, but the plan for what is being done is understood. The plan is not going |
65 | 13 | Boyd, Steven | to (ha) plan due to delays in getting an external contractor. |
66 | ** *Action Item*: We will make some form of water system schedule available (Colin) |
||
67 | * Bellows installation and FC cooldown : Bellows discussed during DC report. We plan to pump the FC down ASAP and then, if happy, |
||
68 | start the cooldown. |
||
69 | * Tracker hall probe installation: Will start tomorrow. Craig and Melissa have a plan which will get the losses down to an acceptable level. This will only take a day or so. |
||
70 | 12 | Boyd, Steven | * AOB |
71 | ** Prescaled trigger discussion: Yordan is organising a phone meeting to develop the prescaled trigger. For those interested there |
||
72 | is a Doodle poll for this meeting. |
||
73 | ** Henry: Still looking for people to train as BLOCs. BLOC training will happen in June. An invitation will be given at the VC. |
||
74 | ** Henry: Water detection in the trench? Pierrick: we have water detection in the trench but it's in the gutter and so shows water |
||
75 | 13 | Boyd, Steven | detection all the time. We need to come up with a proper plan. |
76 | *** *Action Item*: Henry, Craig, Paul and Pierrick to look into optimising this for once and for all. |
||
77 | ** Henry: Can Paul lower the target frame and check that the laser light levels haven't changed. Paul: Yes. |