h1. Ops/Comm Scheduling meeting 

 Location : CR11 in R3 @ 15:30 pm on Tuesday 3rd 

 Phone access :    ReadyTalk number  
 US 866-740-1260 
 UK 0800-496-0576 
 Swiss 0800-70-53-51 
 Italy 800182592 
 Access Code: 2155402 

 h1. Agenda 

 * *Actions from last meeting* 
 ** Generate appropriate table to store absorber pressure and material information    (Janusz) : (almost done) 
 ** DS readback current requires calibration (DL) : stands until close to powerup 
 ** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands 
 ** Move the tracker CAENbus module higher up the chain (Craig) 
 ** Get an estimate for how long it takes to wire in the chiller in (Andy) 

 * DC report 
 * Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx 
 * QP/QD work : http://micewww.pp.rl.ac.uk/attachments/6181/MICE_Electrical_Work_List_25APR16.docx 
 * Water system work plan 
 * Bellows installation and FC cooldown 
 * Tracker hall probe installation 
 * AOB 
 ** Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle: 
 http://doodle.com/poll/wnkk4aevq938keb8 

 * DONM : 10/3/2016 

 h1. Minutes 

 * *Present* : Yordan, Paul H, Paul S, Mike C, Vicky B, Josef F, Colin W, Andy N, Craig M, Steve B, Pierrick H, Ken L 

 * *Actions from last meeting* 
 ** Generate appropriate table to store absorber pressure and material information    (Janusz) : (almost done) 
 ** DS readback current requires calibration (DL) : stands until close to powerup 
 ** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands 
 ** Get an estimate for how long it takes to wire in the chiller in (Andy) : Done - about 3-4 days. 

 * DC report 
 ** Focus coil won't go back in since the bellows have been switched around and now the screw hole tolerances no longer match. 
 ** When John gets back from holiday the FC will be pulled out and the bellows swapped 
 ** Daresbury work went well. An ongoing work plan is shown below 
 ** US team came out with a program of work, some of which can be done but because the racks are not fully commissioned the 
 full program of work can't be completed. 
 ** This week HPC have started to work on the compressor for the DS. They are concerned about the temperature of the air end - it's 
 too hot to touch. They plan to replace this in August. Colin:Can we just buy a new one rather than replace in August? Mike: What we 
 get is effectively new but we should put an order in. Colin:we should do a comprehensive job on fixing the compressor so need to 
 understand this issue.  
 *** *Action Item*: Vicky will investigate the state of the refurbished air end to see what we get for our money. 
 ** Daresbury will allow the US to run into a short this week. 
 ** Alan B : the 20 psi main relief valve for SSU needs replacing. Alan has a replacement but it needs installation. This can happen 
 when John is back next week. 
 * Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-02-Workplan.pdf http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx 
 ** Henry: Water plan goes into period when the DSA is closed. If we turn the water back on we may be in a situation where the 
 water pipes to the conventional magnets could blow. If the DSA is closed we can't get to it. Colin: Good point. Henry: We also 
 need the full ISIS running schedule spreadsheet. Colin:I've got something - I'll send it to you.  
 ** *Action Item*: Colin will put the ISIS dates for run-ups and machine work into his schedules to better reflect available access time. 
 * QP/QD work  
 ** Discussed during the DC report 
 * Water system work plan : Colin:There is no day-by-day plan, but the plan for what is being done is understood. The plan is not going 
 to (ha) plan due to delays in getting an external contractor.  
 ** *Action Item*: We will make some form of water system schedule available (Colin) 
 * Bellows installation and FC cooldown : Bellows discussed during DC report. We plan to pump the FC down ASAP and then, if happy, 
 start the cooldown. 
 * Tracker hall probe installation: Will start tomorrow. Craig and Melissa have a plan which will get the losses down to an acceptable level. This will only take a day or so. 
 * AOB 
 ** Prescaled trigger discussion: Yordan is organising a phone meeting to develop the prescaled trigger. For those interested there 
 is a Doodle poll for this meeting. 
 ** Henry: Still looking for people to train as BLOCs. BLOC training will happen in June. An invitation will be given at the VC. 
 ** Henry: Water detection in the trench? Pierrick: we have water detection in the trench but it's in the gutter and so shows water 
 detection all the time. We need to come up with a proper plan.  
 *** *Action Item*: Henry, Craig, Paul and Pierrick to look into optimising this for once and for all. 
 ** Henry: Can Paul lower the target frame and check that the laser light levels haven't changed. Paul: Yes.