20160503 » History » Revision 12
Revision 11 (Karadzhov, Yordan, 03 May 2016 15:56) → Revision 12/17 (Boyd, Steven, 03 May 2016 16:21)
h1. Ops/Comm Scheduling meeting
Location : CR11 in R3 @ 15:30 pm on Tuesday 3rd
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
h1. Agenda
* *Actions from last meeting*
** Generate appropriate table to store absorber pressure and material information (Janusz) : (almost done)
** DS readback current requires calibration (DL) : stands until close to powerup
** Issues arising from last data taking run need to be identified and actioned (Boyd) : Stands
** Move the tracker CAENbus module higher up the chain (Craig)
** Get an estimate for how long it takes to wire in the chiller in (Andy)
* DC report
* Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx
* QP/QD work : http://micewww.pp.rl.ac.uk/attachments/6181/MICE_Electrical_Work_List_25APR16.docx
* Water system work plan
* Bellows installation and FC cooldown
* Tracker hall probe installation
* AOB
** Prescaled trigger discussion (Online group). If you are interested, please indicate your availability in the doodle:
http://doodle.com/poll/wnkk4aevq938keb8
* DONM : 10/3/2016
h1. Minutes
* Present : Yordan, Paul H, Paul S, Mike C, Vicky B, Josef F, Coli W, Andy N, Craig M, Steve B, Pierrick H
* *Actions from last meeting*
** Generate appropriate table t
* DC report
** Focus coil won't go back in since the bellows have been switched around and now the screw hole tolerances no longer match.
** When John gets back from holiday the FC will be pulled out and the bellows swapped
** Daresbury work went well. An ongoing work plan is shown below
** US team came out with a program of work, some of which can be done but because the racks are not fully commissioned the
full program of work can't be completed.
** This week HPC have started to work on the compressor for the DS. They are concerned about the temperature of the air end - it's
too hot to touch. They plan to replace this in August. Colin:Can we just buy a new one rather than replace in August? Mike: What we
get is effectively new but we should put an order in. Colin:we should do a comprehensive job on fixing the compressor so need to
understand this issue. Action Item: Vicky will investigate the state of the refurbished air end to see what we get for our money.
** Daresbury will allow the US to run into a short this week.
** Alan B : the 20 psi main relief valve for SSU needs replacing. Alan has a replacement but it needs installation. This can happen
when John is back next week.
* Work plan for the next week : http://micewww.pp.rl.ac.uk/attachments/6180/2016-05-03-MICE-Hall-Plan.xlsx
** Henry: Water plan goes into period when the DSA is closed. If we turn the water back on we may be in a situation where the
water pipes to the conventional magnets could blow. If the DSA is closed we can't get to it. Colin: Good point. Henry: We also
need the full ISIS running schedule spreadsheet. Colin:I've got something - I'll send it to you. Action Item: Colin will put the
ISIS dates into his schedules including run up.
* QP/QD work
* Water system work plan : Colin:There is no day-by-day plan, but the plan for what is being done is understood. The plan is not going
to plan due to delays in getting an external contractor. We'll put a project plan up here.
* Bellows installation and FC cooldown : Colin:We can plan to pump the FC down and get it as dry as it can. Is there any reason
to start cooling once it's pumped down. Josef: we can do this. Colin:once we're happy then we can start the coolers.
* Tracker hall probe installation: Alan: Will start tomorrow - we have a plan which will get the losses down to an acceptable level.
* AOB
** Prescaled trigger discussion: Yordan is organising a phone meeting to develop the prescaled trigger. For those interested there
is a Doodle poll for this meeting.
** Henry: Still looking for people to train as BLOCs. BLOC training will happen in June. An invitation will be given at the VC.
** Henry: Water detection in the trench? Pierrick: we have water detection in the trench but it's in the gutter and so shows water
detection all the time. We need to come up with a proper plan. Action Item: Henry, Craig, Paul and Pierrick to look into optimising
this for once and for all.
** Henry: Can Paul lower the target frame and check that the laser light levels haven't changed. Yes.