Commissioning and Ops Scheduling meeting : 9/2/2016¶
To be held in CR10 in the ATLAS Building @ 15:30 pm
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Agenda:¶
- Review of tasks and activities identified at last meeting
- Action Item : John will continue to investigate pathologies in scattering plots
- Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
- Action Item : Steve to talk to Alan Stevens about stopping 4-hourly monitoring but leaving the alarm in place
- Alan replied and is quite happy to stop the 4 hourly checks, but keep the alarm in the ISIS CR
- Action Item : Colin, Trevor, Steve, Pierrick to have a meeting to review the Daresbury work schedule in light of running time
and the currently known state of the SS work. Meeting to happen on morning of Thursday 28th.- Action stands
- Action Item : Steve/DC/Andy to think about organisation during mixed work sessions
- Action stands
- Action Item Steve/Colin to talk to the tracker group and request action plan
- Tracker group contacted and report will be made at the meeting. See discussion below
- Action Item Andy/Colin/DC to think about the procedure of running with SC permit with the PRY open (@ 10 A and with
sanction from the US team)- A procedure exists. We should check that it has been run past Andy.
- Current and near future activities
- DS Cooldown and PS return schedule
- Preparation for realignment work
- Focus coil installation and vacuum test schedule
- Tracker patch panel leak work and schedule
- Controls and Monitoring : Network reconfiguration and testing
- Daresbury work schedule
- List of things to address before February run
- Operational Schedule
- Expert led run : Feb 17th. Hall to be left closed overnight
- Beam tuning from 10 am on Feb 18th
- Data-taking nominally begins on the 23rd with shift training on the 22nd.
- AOB
- Chair of meetings for next 5 weeks
Minutes¶
Present: Josef B, Paul H, Vicky B, Steve B, Paul K, P. Franchini, Mark T, John C, Ed O, John G,
Henry N, Pierrick H, Ryan B
- Review of tasks and activities identified at last meeting
- Action Item : John will continue to investigate pathologies in scattering plots
- John is looking into this but no result at this meeting
- Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
- A pull-down list on run control will let the shifters define the absorber to be used in each run
- pressure sensors are available and will be read out into CDB
- Action Item : Steve to talk to Alan Stevens about stopping 4-hourly monitoring but leaving the alarm in place
- Alan replied and is quite happy to stop the 4 hourly checks, but keep the alarm in the ISIS CR
- Action Item : Colin, Trevor, Steve, Pierrick to have a meeting to review the Daresbury work schedule in light of running time
and the currently known state of the SS work. Meeting to happen on morning of Thursday 28th.- Action stands
- Action Item : Steve/DC/Andy to think about organisation during mixed work sessions
- Action stands
- Action Item Steve/Colin to talk to the tracker group and request action plan
- see below
- Action Item Andy/Colin/DC to think about the procedure of running with SC permit with the PRY open (@ 10 A and with
sanction from the US team)- Action stands
- Action Item : John will continue to investigate pathologies in scattering plots
- Current and near future activities
- DS Cooldown and PS return schedule
- Decay solenoid is cooling down with no problems. It is expected to be cold around the end of this week.
- DS PS will return by end of next week. Trevor would like Mike to inspect the PS before installation on the mezzanine.
- Commissioning is planned for 29th Feb - 3rd Mar, and 8th-11th Mar
- Calibration of current will be done during tests
- Preparation for realignment work
- MIPO have agreed to postpone the manual realignment until the end of the user cycle
- Focus coil installation and vacuum test schedule
- Jon Duffy working on FC1 in the Hall and getting it ready and he is close. This will
take until the end of this week. - FC can't be put into the channel until the work on the tracker leak is done however.
- Jon Duffy working on FC1 in the Hall and getting it ready and he is close. This will
- Tracker patch panel leak work and schedule
- (Long long discussion, summarised as)
- There are three areas where He leaks from the tracker : the Hall probe connectors, the patch panel and the diffuser.
- Leaks from the connectors and patch panel will be dealt with this week
- Repair of diffuser leak is more involved and requires expert effort from Oxford. We need quantitative estimates of the
- leak rate to judge how important this is.
- Tenatively plan diffuser leak repair in the day of the 28th Feb - 3rd Mar.
- Controls and Monitoring : Network reconfiguration and testing
- Pierrick is rebuilding all the IOCs. We will finish this week so will be able test by 16th.
- Intention is to be ready for the expert led run on the 17th.
- Daresbury work schedule
- See above
- SS dump trays to be taken back to Daresbury this week
- DS Cooldown and PS return schedule
- List of things to address before February run
- Quick run through of this list
- Action Item : Steve to email responsible to get this list up to date
- Operational Schedule
- Expert led run : Feb 17th. Hall to be left closed overnight
- Beam tuning from 10 am on Feb 18th
- Data-taking nominally begins on the 23rd with shift training on the 22nd.
- AOB
- Henry reminded us that the Hall walkthrough on the 22nd should also include RF crew
- Paul informed us that there will be a visit by school children sometime in March and will need a Hall tour.
- Chair of meetings for next 5 weeks
- Steve is teaching at this time for the next 5 weeks. DC will chair the meeting.