Commissioning and Ops Scheduling meeting : 2/2/2016

To be held in CR10 in the ATLAS Building @ 15:30 pm

Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402

Agenda:

  • Review of tasks and activities identified at last meeting
    • Action Item : John will look at the effect of air on the MC truth scattering angle
    • Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
      • Action Item : DC to work with Pierrick to ensure this
    • Action Item : Steve to talk to Alan Stevens about stopping 4-hourly monitoring but leaving the alarm in place
    • Action Item : Paolo, Mike and Vicky will investigate the Linde fridge PC instability issue
    • Action Item : Paolo/Pierrick will think of a way to monitor the Linde fridge PC
    • Action Item : Andy/DC will organise the magnetic sweep
    • Action Item : Colin, Trevor, Steve, Pierrick to have a meeting to review the Daresbury work schedule in light of running time
      and the currently known state of the SS work. Meeting to happen on morning of Thursday 28th.
  • Updates and future schedule
    • DS Cooldown schedule
    • Realignment work and schedule
    • Cooling water discussion
    • Controls and Monitoring : Network reconfiguration
    • Tracker patch panel leak work
    • Electrical work schedule
    • Data-taking schedule