Project

General

Profile

20160126 » History » Version 2

Boyd, Steven, 25 January 2016 09:20

1 1 Boyd, Steven
h1. Commissioning and Ops Scheduling meeting : 26/1/2016
2
3
To be held in CR10 in the ATLAS Building @ 15:30 pm 
4
5
Phone access :  ReadyTalk number 
6
US 866-740-1260
7
UK 0800-496-0576
8
Swiss 0800-70-53-51
9
Italy 800182592
10
Access Code: 2155402
11
12
h2. Agenda:
13
14
* Review of tasks and activities identified at last meeting
15
** Realignment work
16
*** *Action Item (Colin to prod John C)* : need to get John's data with fiducials in it to get to Tony Middleton.
17
** Simulation of material in the interspace
18
*** *Action Item* : John to give these files to the tracker group to make certain tracker resolution doesn't change
19
*** *Action Item* : John to do a simulation with air in the interspace and He in the absorber volume
20
*** *Action Item* : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded 
21
*** *Action Item* : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
22
** Cooling water discussion
23
*** *Action Item* : Colin and John to talk and agree on the plan.
24
** ISIS Monitoring of SS magnets
25
*** *Action Item* : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
26
** BLOCS and SOCS
27 2 Boyd, Steven
*** *Action Item* : -Steve to remind Adam that we need SOCs.-
28 1 Boyd, Steven
** DS PS Installation
29
*** *Action Item* : Colin is to get an estimate for power supply installation time.
30
* Upcoming and ongoing activities : chaired by DC
31
** "Operations calendar":https://www.google.com/calendar/embed?src=miceops%40gmail.com&ctz=Europe/London
32
** C&M network reconfiguration
33
* AOB
34
* Date of next meeting : February 2nd
35
36
37
h2. Minutes