h1. Commissioning and Ops Scheduling meeting : 26/1/2016
2
3
To be held in CR10 in the ATLAS Building @ 15:30 pm 
4
5
Phone access :  ReadyTalk number 
6
US 866-740-1260
7
UK 0800-496-0576
8
Swiss 0800-70-53-51
9
Italy 800182592
10
Access Code: 2155402
11
12
h2. Agenda:
13
14
* Review of tasks and activities identified at last meeting
15
** Realignment work
16 8 Boyd, Steven
*** *Action Item (Colin to prod John C)* : need to get John's data with fiducials in it to get to Tony Middleton. _Expected yesterday_
17 1 Boyd, Steven
** Simulation of material in the interspace
18
*** *Action Item* : John to give these files to the tracker group to make certain tracker resolution doesn't change
19
*** *Action Item* : John to do a simulation with air in the interspace and He in the absorber volume
20
*** *Action Item* : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded 
21
*** *Action Item* : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
22
** Cooling water discussion
23 9 Boyd, Steven
*** *Action Item* : Colin and John to talk and agree on the plan. _Discussion complete but further work needed_
24 1 Boyd, Steven
** ISIS Monitoring of SS magnets
25
*** *Action Item* : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
26
** BLOCS and SOCS
27 2 Boyd, Steven
*** *Action Item* : -Steve to remind Adam that we need SOCs.-
28 1 Boyd, Steven
** DS PS Installation
29 8 Boyd, Steven
*** *Action Item* : Colin is to get an estimate for power supply installation time. _2 sets of 2-3 days over a space of 2 weeks_
30 1 Boyd, Steven
* Upcoming and ongoing activities : chaired by DC
31
** "Operations calendar":https://www.google.com/calendar/embed?src=miceops%40gmail.com&ctz=Europe/London
32
** C&M Network reconfiguration
33 14 Boyd, Steven
** Realignment work schedule
34 13 Boyd, Steven
** Tracker patch panel leak work
35 10 Boyd, Steven
** Date of DSA closure and work required before hand
36 3 Boyd, Steven
** "Henry's January workplan":http://micewww.pp.rl.ac.uk/projects/operations/wiki/WorkPlanJanuary2016
37 1 Boyd, Steven
** "Daresbury workplan":http://micewww.pp.rl.ac.uk/attachments/5602/MICE_Work_List_18-01-16_v2_1.pdf
38
* AOB
39
* Date of next meeting : February 2nd
40
41
42
h2. Minutes
43 15 Boyd, Steven
44
Present: Andy, Vicky Bayliss, Paolo, Durga, Chris R, Steve B, Paul K, Trevor H, Jaroslaw, Mike C, Victoria, John N, Paul H,  Henry N, Ken L
45
46
h3. Review of action items
47
48
* Realignment work
49
** *Action Item (Colin to prod John C)* : need to get John's data with fiducials in it to get to Tony Middleton. _Expected yesterday_
50 18 Boyd, Steven
*** _Done_
51 15 Boyd, Steven
* Simulation of material in the interspace
52
** *Action Item* : John to do a simulation with air in the interspace and He in the absorber volume
53 18 Boyd, Steven
*** _John presented plots to show that there is little effect. However, these plots include systematic effects in the reconstruction
54
that are being worked on._
55
*** _*Action Item* : John will look at the effect of air on the MC truth scattering angle_
56 15 Boyd, Steven
** *Action Item* : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded 
57 18 Boyd, Steven
*** _*Action Item* : DC to work with Pierrick to ensure this_
58 15 Boyd, Steven
** *Action Item* : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
59 18 Boyd, Steven
*** _Alan says that the LiH absorber can withstand vacuum._ 
60 15 Boyd, Steven
* Cooling water discussion
61
** *Action Item* : Colin and John to talk and agree on the plan. 
62 18 Boyd, Steven
*** _Discussion complete but further work needed_
63 15 Boyd, Steven
* ISIS Monitoring of SS magnets
64
** *Action Item* : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
65 18 Boyd, Steven
*** _Josef doesn't think we need to monitor to the level we are doing now. Proposed to stop the 4-hour monitoring and just leave
66
the buzzer in the control room._
67 17 Boyd, Steven
*** *Action Item* : Steve to talk to Alan Stevens about this possibility-
68 15 Boyd, Steven
* BLOCS and SOCS
69
** *Action Item* : Steve to remind Adam that we need SOCs.
70 18 Boyd, Steven
*** _Done_
71 15 Boyd, Steven
* DS PS Installation
72
** *Action Item* : Colin is to get an estimate for power supply installation time. 
73 18 Boyd, Steven
*** _2 sets of 2-3 days over a space of 2 weeks._
74 15 Boyd, Steven
75
h3. Updates and future schedule
76
77
* Trevor outlined the DS PS return schedule. The PS is expected to return in mid-February (8th - 15th). He plans to start commissioning