Commissioning and Ops Scheduling meeting : 26/1/2016¶
To be held in CR10 in the ATLAS Building @ 15:30 pm
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Agenda:¶
- Review of tasks and activities identified at last meeting
- Realignment work
- Action Item (Colin to prod John C) : need to get John's data with fiducials in it to get to Tony Middleton. Expected yesterday
- Simulation of material in the interspace
- Action Item : John to give these files to the tracker group to make certain tracker resolution doesn't change
- Action Item : John to do a simulation with air in the interspace and He in the absorber volume
- Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
- Action Item : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
- Cooling water discussion
- Action Item : Colin and John to talk and agree on the plan. Discussion complete but further work needed
- ISIS Monitoring of SS magnets
- Action Item : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
- BLOCS and SOCS
- Action Item :
Steve to remind Adam that we need SOCs.
- Action Item :
- DS PS Installation
- Action Item : Colin is to get an estimate for power supply installation time. 2 sets of 2-3 days over a space of 2 weeks
- Realignment work
- Upcoming and ongoing activities : chaired by DC
- Operations calendar
- C&M Network reconfiguration
- Realignment work schedule
- Tracker patch panel leak work
- Date of DSA closure and work required before hand
- Henry's January workplan
- Daresbury workplan
- AOB
- Date of next meeting : February 2nd
Minutes¶
Present: Andy, Vicky Bayliss, Paolo, Durga, Chris R, Steve B, Paul K, Trevor H, Jaroslaw, Mike C, Victoria, John N, Paul H, Henry N, Ken L
Review of action items¶
- Realignment work
- Action Item (Colin to prod John C) : need to get John's data with fiducials in it to get to Tony Middleton. Expected yesterday
Done
- Action Item (Colin to prod John C) : need to get John's data with fiducials in it to get to Tony Middleton. Expected yesterday
- Simulation of material in the interspace
- Action Item : John to do a simulation with air in the interspace and He in the absorber volume
John presented plots to show that there is little effect. However, these plots include systematic effects in the reconstruction
that are being worked on.Action Item : John will look at the effect of air on the MC truth scattering angle
- Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
Action Item : DC to work with Pierrick to ensure this
- Action Item : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
Alan says that the LiH absorber can withstand vacuum.
- Action Item : John to do a simulation with air in the interspace and He in the absorber volume
- Cooling water discussion
- Action Item : Colin and John to talk and agree on the plan.
Discussion complete but further work needed
- Action Item : Colin and John to talk and agree on the plan.
- ISIS Monitoring of SS magnets
- Action Item : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
- -Josef doesn't think we need to monitor to the level we are doing now. Proposed to stop the 4-hour monitoring and just leave
the buzzer in the control room. - Action Item : Steve to talk to Alan Stevens about this possibility-
- -Josef doesn't think we need to monitor to the level we are doing now. Proposed to stop the 4-hour monitoring and just leave
- Action Item : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
- BLOCS and SOCS
- Action Item : Steve to remind Adam that we need SOCs.
Done
- Action Item : Steve to remind Adam that we need SOCs.
- DS PS Installation
- Action Item : Colin is to get an estimate for power supply installation time.
2 sets of 2-3 days over a space of 2 weeks.
- Action Item : Colin is to get an estimate for power supply installation time.
Updates and future schedule¶
- Trevor outlined the DS PS return schedule. The PS is expected to return in mid-February (8th - 15th). He plans to start commissioning
the new PS on Feb 22nd. This could roll into the next week.
Updated by Boyd, Steven about 7 years ago · 17 revisions