1 | 1 | Boyd, Steven | h1. Commissioning and Ops Scheduling meeting : 26/1/2016 |
---|---|---|---|
2 | |||
3 | To be held in CR10 in the ATLAS Building @ 15:30 pm |
||
4 | |||
5 | Phone access : ReadyTalk number |
||
6 | US 866-740-1260 |
||
7 | UK 0800-496-0576 |
||
8 | Swiss 0800-70-53-51 |
||
9 | Italy 800182592 |
||
10 | Access Code: 2155402 |
||
11 | |||
12 | h2. Agenda: |
||
13 | |||
14 | * Review of tasks and activities identified at last meeting |
||
15 | ** Realignment work |
||
16 | 8 | Boyd, Steven | *** *Action Item (Colin to prod John C)* : need to get John's data with fiducials in it to get to Tony Middleton. _Expected yesterday_ |
17 | 11 | Boyd, Steven | *** Schedule of work |
18 | 1 | Boyd, Steven | ** Simulation of material in the interspace |
19 | *** *Action Item* : John to give these files to the tracker group to make certain tracker resolution doesn't change |
||
20 | *** *Action Item* : John to do a simulation with air in the interspace and He in the absorber volume |
||
21 | *** *Action Item* : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded |
||
22 | *** *Action Item* : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum |
||
23 | ** Cooling water discussion |
||
24 | 9 | Boyd, Steven | *** *Action Item* : Colin and John to talk and agree on the plan. _Discussion complete but further work needed_ |
25 | 1 | Boyd, Steven | ** ISIS Monitoring of SS magnets |
26 | *** *Action Item* : Josef/Colin to check with Alan about monitoring requirements for the SS magnets. |
||
27 | ** BLOCS and SOCS |
||
28 | 2 | Boyd, Steven | *** *Action Item* : -Steve to remind Adam that we need SOCs.- |
29 | 1 | Boyd, Steven | ** DS PS Installation |
30 | 8 | Boyd, Steven | *** *Action Item* : Colin is to get an estimate for power supply installation time. _2 sets of 2-3 days over a space of 2 weeks_ |
31 | 1 | Boyd, Steven | * Upcoming and ongoing activities : chaired by DC |
32 | ** "Operations calendar":https://www.google.com/calendar/embed?src=miceops%40gmail.com&ctz=Europe/London |
||
33 | 12 | Boyd, Steven | ** C&M Network reconfiguration |
34 | 13 | Boyd, Steven | ** Tracker patch panel leak work |
35 | 10 | Boyd, Steven | ** Date of DSA closure and work required before hand |
36 | 3 | Boyd, Steven | ** "Henry's January workplan":http://micewww.pp.rl.ac.uk/projects/operations/wiki/WorkPlanJanuary2016 |
37 | 1 | Boyd, Steven | ** "Daresbury workplan":http://micewww.pp.rl.ac.uk/attachments/5602/MICE_Work_List_18-01-16_v2_1.pdf |
38 | * AOB |
||
39 | * Date of next meeting : February 2nd |
||