Commissioning and Ops Scheduling meeting : 26/1/2016¶
To be held in CR10 in the ATLAS Building @ 15:30 pm
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Agenda:¶
- Review of tasks and activities identified at last meeting
- Realignment work
- Action Item (Colin to prod John C) : need to get John's data with fiducials in it to get to Tony Middleton.
- Simulation of material in the interspace
- Action Item : John to give these files to the tracker group to make certain tracker resolution doesn't change
- Action Item : John to do a simulation with air in the interspace and He in the absorber volume
- Action Item : Pierrick/Mark - ensure that the pressure and material in the absorber volumes are recorded
- Action Item : Colin will check with Alan Bross whether the LiH absorber can withstand vacuum
- Cooling water discussion
- Action Item : Colin and John to talk and agree on the plan.
- ISIS Monitoring of SS magnets
- Action Item : Josef/Colin to check with Alan about monitoring requirements for the SS magnets.
- BLOCS and SOCS
- Action Item : Steve to remind Adam that we need SOCs.
- DS PS Installation
- Action Item : Colin is to get an estimate for power supply installation time.
- Realignment work
- Upcoming and ongoing activities : chaired by DC
- Operations calendar
- C&M network reconfiguration
- AOB
- Date of next meeting : February 2nd