Commissioning and Ops Scheduling meeting : 15/12/2015¶
To be held in CR10 in the ATLAS Building @ 15:30 pm
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Agenda:¶
- Review of tasks and activities identified at last meeting
- Vacuum / Hydrogen system work : Mark Tucker
- Running with Xe in the absorber : MOM
- Upcoming activities : chaired by DC
- This week's MICE Hall work plan (Craig)
- Evacuating absorber to provide a baseline scattering measurement : do we and when?
- Activities after running finishes on Friday 18th
- test of the Q4 flush - take magnet to high current and see if it trips.
- Temperature readout investigation/swap of Q4 / Q5 sensors (Henry)
- 50A test on the DS (Mike)
- Network reconfiguration for C&M. It is estimated that this may take up to a week of work. When do we schedule?
- Christmas shutdown schedule and plans : when is "end of play"?
- What needs to be made safe before leaving for Christmas?
- AOB
- To-do list for Maintenance shutdown (January 2016)
- Date of next meeting : January 5th
Minutes¶
Present: Craig, Chris R, Paolo, Ryan, Victoria, Colin,
Review :¶
- Colin hopes that the vacuum work for North side is finished.
- Absorber group are planning to meet tomorrow morning to schedule their activities
- Absorber filled with Xe on Friday. All is stable and we have been taking data smoothly since Sunday.
Upcoming activities :¶
Next week's work plan :¶
- Activities post-Thursday will probably involve preparation to take FC2 out to get at the absorber to fix it.
- Beam ends on Friday @ 8 am. Data-taking will stop at 10 pm on the previous evening.
- We decided to remove the Xe to get a reference data set with an empty absorber. This will happen on Thursday morning.
- Test of Q4 flush and Temperature readout for Q5 / Q6 will be managed by Henry on Friday 18th.
- Pierrick requests half a day with the FC at low current. Will discuss with Colin and the absorber team tomorrow.
- Network configuration for C&M : early to mid January but needs dates to lock it down.
- Action: ask Pierrick to produce a document on what changes are needed in the network configuration so that system owners
understand the impact. This should be emailed to system owners ASAP.
- Action: ask Pierrick to produce a document on what changes are needed in the network configuration so that system owners
Christmas shutdown plans : what needs to be done by Friday and what to monitor over Christmas (Victoria)¶
- We have designated end of Wednesday 23rd as "end of play"
- Victoria will organise the shutdown checklist by looking at the old MOM walkabout list and then considering the new systems.
Amongst other things that need monitoring over Christmas are- Helium levels and pressure in solenoids
- Focus coil state
- Cerenkov gas flow
- Water in quads
January plans¶
- A discussion of plans shown in the To-do list was discussed. Timeline and action items can be found
on that page.