Commissioning and Ops Scheduling meeting : 1/12/2015
2
3
To be held in CR10 in the ATLAS Building @ 15:30 pm 
4
5
Phone access :  ReadyTalk number 
6
US 866-740-1260
7
UK 0800-496-0576
8
Swiss 0800-70-53-51
9
Italy 800182592
10
Access Code: 2155402
11
12
h2. Agenda:
13
14
* Review of tasks and activities identified at last meeting
15 2 Boyd, Steven
** Focus coil progress and soak test
16 1 Boyd, Steven
** Decay Solenoid PSU Repair
17 2 Boyd, Steven
** Hydrogen/Vacuum system work
18
* Upcoming activities : chaired by Victoria/Paul
19 3 Blackmore, Victoria
** "This week's MICE Hall work plan":http://micewww.pp.rl.ac.uk/attachments/download/5295
20 2 Boyd, Steven
** Focus coil operation
21 1 Boyd, Steven
** Hydrogen/Vacuum system installation and commissioning
22 3 Blackmore, Victoria
** Hydrogen alarm system work (requires roof access Tues--Fri)
23 4 Boyd, Steven
** Hall investigation for visual survey of X-ray leakage and reflection paths : Wed 10:30 am - 11:30 am (requires roof access)
24 3 Blackmore, Victoria
** Nitrogen system work (Tues--Thurs)
25
** North-side handrail installation (Wed am)
26 5 Boyd, Steven
* Operations plan 
27 7 Boyd, Steven
** Thursday 3rd (2 pm - 10 pm) : Noon run plan meeting / Close Hall / Beam tune / Prep data-taking / Take TOF 0 calibration (Q789 off) / FC off data / Open Hall
28 5 Boyd, Steven
** Friday 4th ( 12pm - 8 pm ) : 9 am Run plan meeting / Close Hall / Magnetic sweep / Ramp FC to 50 A Flip mode / FC on data-taking / Go to Standby overnight
29 8 Boyd, Steven
** Saturday 5th ( 9 am - 4 pm ) : 9 am Run Plan meeting / 10 am Ramp FC to 100 A / FC-on data taking / Go to standby overnight
30
** Sunday 6th ( 9 am - 4 pm ) : 9 am Run Plan meeting / 10 am Ramp to 150 A / FC-on data-taking / Go to Standby overnight
31
** Monday 7th ( 9 am - end ) : 9 am run plan meeting / 10 am Ramp FC to 0 A / Take FC-off data / End and Open Hall
32 5 Boyd, Steven
* Questions
33
** When can we start operations on Friday?
34
** FC expert availability on Sat/Sun (drives when ramps can happen)
35
** Hall activities on morning of Monday 7th
36
37 1 Boyd, Steven
* AOB
38
** [[WorkPlanJanuary2016|To-do list]] for Maintenance shutdown (January 2016)