Friday Operations Meeting : 24/4/2015

  • Review of Evening Debugging Runs

Special thanks to Yordan, Durga, Francoise and Pierrick for spending long hours in the CR over the
last week helping to make the system run

  • Weekend Operations Running Mode : New or old Trigger Configuration

We will run the new system, which implies that we need to take a TOF calibration run, hopefully on Friday night

  • General comments about control room activities arising from last weekend run
    • Please be methodical when going through checklists and ensure that all steps are carried out. (All)
    • Enhance written Elog error messages so that physics shifter has a better idea of what went wrong and whether it is serious. Include error
      message in Elog entry (All)
    • Remember to fill in the Shift Summary at the end of every shift. Information should include :
      • Date and Shift (morning, afternoon, night)
      • Name of shifters, BLOC, SOC and MOM
      • Status of ISIS during the shift
      • Summary of runs taken (run number, run configuration, any other short comment on run)
    • for the moment we will keep the Run Summary Spreadsheet going in parallel with the CDB (to be reviewed every week)
      Check CDB after each run - put in Chris shift checklist. The CDB viewer can be found here
  • Request to experts on site : Saturday morning readiness check

All agree to be available on Saturday morning to bring the system up.

  • Today's plans
    • BLOC Training
    • Trainees : Alan Young
    • Control room training : 12:00 pm
    • Hall closure : 1:00 pm : Full PPS tutorial required