20150308 RunPreparationList¶
- Create a run plan page in the repository
- How many muons will be needed? How much data will this generate at 100 kB each? (#900)
- Decide how many days you need
- What detector calibration runs will be needed?
- Schedule updated surveys if equipment has been moved [**] 2 months before running
- Notify Henry Nebrensky (for Data Mover cover and data volume, and BLOC cover), and Durga Rajaram (computing cover) 1 month before running
- Request shifter and on-call cover
- Notify Mike Courthold, as Decay Solenoid cool-down must start 2 weeks before running
- Make a request to ISIS for data taking (1 week before running)
- inform Paul Wright, who is the site Radiation Protection Advisor, by email of start and finish times of each MICE experimental run.
He has also requested that T-type dosimeters be placed at various points within the Hall - he will organise and take charge of that. - Ensure up-to-date documentation and checklists in MLCR
- Check Hall air-conditioning units all work
- Check beamline polarity and get it changed if needed
- Check POMPOM voltage and make sure is correct at 12 V
- Check ISIS software applications and logins still work
- Check DS turret fan is running [**]
- Ask Pierrick to change Run Control over to production ConfigDB instance
- Locate latest run summary spreadsheet
- Check PPS doors/BOBs OK
- Check target frame movement [**]
- Turn on SY527 and SY127 HV supplies
- Cranes moved to West end of Hall (away from ISIS)
- Erect temporary fencing around Q789/TOF1, around TOF2/KL, and across gap by sliding floors
- Paperwork
- Authorization to Work (ATWs) in Collaboration with Andy Nichols
- Go to http://miceserv1.micenet.rl.ac.uk/updates and disable auto-updates
N.B. Items ** may need DSA or ISIS access to rectify any problems