Actions
Operations Meeting, in Preparation for Mock Data Run¶
Pierrick
Steve
Adam Dobbs
Ed Overton
David Adey
Chris Rogers
Yordan Karadzhov
- IOC is running
- State machine is near completion, needs testing
- Run control using the state machine needs to be tested
- Hardware all okay
- HV can't be run on remote
- HV test on Ckov
- PMTs all okay
- Cryo - 3+4 are cold (D/S), only these will get wave guide on
- Cryo - probably cold by Friday
- Waveguides need to be in; waiting on John Govans to bring them over on forklift
- Cabling of D/S tracker this afternoon
- Ground the cryostats
- Short to be fixed on cryo 3
- CAEN VME controller needs to be switched to D/S rack, currently they are in the U/S rack
- D/S ones are in Sheffield
- Or use SVS; SVS is regarded as a fallback
- Round of initialisations and simple standalone readout tomorrow
- Use current Adey C+M to drive DAQ
- Merge tracker code in with DATE
- Attempt to readout, using old trigger
- Attempt to bring in new trigger, need to get to that in next two days
- Yordan will test Overton FPGA code
- Use LED system once Alan and Paul arrive on Friday
- Tracker Controls
- Merging James's non-expert code; Ed and Pierrick, following TOF HV
- Hardware things; CAEN controller, moving back to SVS is possible but not tested, CAEN controller is not tested; Pierrick casts doubt on possibility
- Need to run a new fibre next few days, 3 fibres spare
- Daresbury needs to finish readout of MKS (vacuum) and temp controllers
- Need interlock CANBus fixed
- Unpacking
- No change
- OnMon
- Adey has spoken with Rhys, he will be here later this week to discuss
- OnRec
- Dobbs and Adey requested status separately from Melissa, no reply
- No change
- Rogers to chase
- Run plan
- Need to introduce appropriate delays on LED before it hits the trigger
- LED needs to pulse first
- No known problems; it is on SYV527
- Two front end boards noisy need replacing
- Missing power supply for LED
- No known issues
- Pierrick, when he was installing the IOC trace, he noticed the LM power supply came disconnected; need to check that it has not been damaged
- Check voltages on PMTs
- Look for dark currents off the PMT
- No known problems
- New machines
- New DATE
- New linux install
- General tests, but all looked okay
- Need to test with real data
- EMR control and monitoring of rack is likely to slip
- Failed disk on miceserv
- micethin network broken
- niggles
- NAGIOS deployment
- Network switch okay
- Reset of a mice thin may break network connection
- Need to update movefiles script; change to Step IV
- Not expecting automated data mover to run
- Janusz will be around on 21st January
- Nothing new
- Note that beam stop will be closed for PPS reasons while the target is operating
- Target - S1.9 is now installed, few niggles
- Will do testing on fibres
- Swap controller with R78 controller
- Check quadrature
- Run up target before Friday lunchtime
- Need to check with ISIS that there is vacuum
- Decay solenoid
- Attempting to fix DS trip on low current this week
- Currently DS is at 200 A; after today it will be owned by expert
- Should be in the hall, may be tripping off fridge, need to have easy access to MLCR/Linde fridge PC
- NC magnets
- Water from ISIS is marginal, may cause problem
- Fenced and signs still up in synch, Henry to take signs down later today following tests
- Beamstop serviced and working
- Need to be closed for D1 and D2 and target frame lowered
- Proton absorber
- No known issues
- Go through with Adam after lunch on Wednesday 14.30 onwards
- No request for SOC
- Action on onrec to move onrec02 and 03 into the server
Updated by Rogers, Chris over 8 years ago ยท 1 revisions