Dashboard 170714

16 July 2014 16:18

Critical and Near

16 July 2014 16:19

Delivering the MICE project; options for success

04 August 2014 17:48

This document presents an overview of the information prepared for the DOE review of MAP and MICE to be held at Brookhaven National Laboratory on the 12th--14th August 2014.

Magnet and Beam Commissioning at Step IV

04 August 2014 16:17

Magnet and Beam Commissioning at Step IV

Planning the MICE Step IV Data Campaign

04 August 2014 16:31

Planning the MICE Step IV Data Campaign

MICE Project Assumptions Document

04 August 2014 17:49

Project-level assumptions document; issue 1, draft 2.

MICE Hall Pictures

07 August 2014 15:01

Resource Loaded Schedule, costs and risks to complete MICE

10 November 2014 19:59

Project summary prepared for the November 2014 RLSR Panel review of the MICE project.

Fill title of the document is: Resource Loaded Schedule, costs and risks for the completion of the MICE project

Tracking milestones for the completion of the MICE project

25 November 2014 15:36

Tracking milestones for the completion of the MICE project prepared for the rebaselining of the project at the November 2014 RLSR/MPB.

MICE bimonthly project update #1

02 February 2015 09:56

First bimonthly report on the progress of the MICE project to the Resource Loaded Schedule Review panel.

MICE bimonthly project update #2

08 June 2015 20:28

This, second, bimonthly progress report presents the status of the project at the end of May 2015.

MICE bimonthly project update #3

08 August 2015 18:41

This, the third bimonthly progress report, presents the status of the project at the end of July 2015. The updated
project dashboard may be found at http://micewww.pp.rl.ac.uk/dashboard/.

MICE bimonthly project update #4

03 October 2015 18:11

4th bimonthly report to the MICE Project Board.

Resource Loaded Schedule, costs and risks to complete MICE

20 October 2015 09:46

Report prepared for submission to the Resource Loaded Schedule Review panel for its meeting in October 2015.

Response to recommendations of the RF system review

23 December 2015 14:58

This document presents the MICE project team's response to the recommendations contained in the slides presented in the close-out of the review of the MICE RF power system held on the 9th and 10th of September 2015.

MICE bimonthly project update #5

29 January 2016 08:28

Fifth bimonthly report to the MICE Project Board

MICE Magnet system “readiness” review

05 August 2016 17:31

Report from the Magnet Readiness Review Panel which met at RAL on 28Jun16.

MICE bimonthly project update #6

10 August 2016 16:31

Sixth bimonthly report to the MICE Project Board.

MICE bimonthly project update 7

08 January 2017 13:27

Seventh bimonthly progress report.

Resource Loaded Schedule, costs and risks to complete MICE

28 February 2017 02:20

Report on the cost and schedule to complete the MICE experiment prepared for the April 2017 meeting of the Resource Loaded Schedule Review panel.