Documents
User documentation
Definition of the MIPO and MEMO
24 March 2014 15:38
Management of the MICE construction, maintenance, operations and analysis activities
Response to feedback from the RLSR and MPB
10 November 2014 21:21
Actions and recommendations from the Resource Loaded Schedule Review panel and the MICE Project Board.
Response to feedback from the RLSR panel and MPB
25 July 2014 12:07
Response to the feedback from the April 2014 meetings of the RLSR panel and the MPB.
MICE report to the MICE Project Board
11 November 2014 17:49
MICE report to the MICE Project Board prepared for the November 2014 review of the project.
Response to feedback from the RLSR panel and the MPB
02 February 2015 11:28
Response to the recommendations and actions from the November 2014 Resource Loaded Schedule Review panel and the MICE Project Board.
Response to feedback from the RLSR panel and the MPB
08 June 2015 20:49
This document provides responses to the action and recommendations contained in the feedback from the April 2015 Resource Loaded Schedule Review panel's and the MICE Project Board's review of the project.
Review of the MICE beam-dynamics analysis
19 October 2015 18:44
Terms of reference for the 2015 review of the MICE beam-dynamics analysis.
MICE report to the MICE Project Board
21 October 2015 00:39
Progress report prepared for the October 2015 meeting of the MICE Project Board.
Review of the MICE beam-dynamics analysis
17 December 2015 09:59
Terms of reference for the Review of the MICE beam-dynamics analysis that will take place on the 14th and 15th January 2016.
Response to feedback from the RLSR panel and the MPB
22 January 2016 10:26
Response to feedback from the Resource Loaded Schedule Review panel and the MICE Project Board following the review meetings in October 2016.
Response to feedback from the MICE Optics Review
21 April 2016 09:24
Response to feedback from the MICE Optics Review held at RAL on the 14th and 15th of January 2016.
Response to feedback from the RLSR panel and the MPB
22 April 2016 18:50
Response to feedback from the Resource Loaded Schedule Review panel and the MICE Project Board following the review meetings in April 2016.
Progress in redefining the scope of the cooling demo
21 May 2016 20:23
Memorandum to C.Jamieson of the STFC documenting the status of work on the identifying a reduced risk, reduced cost cooling-demonstration configuration.
Brief specification of the MICE cooling demonstration
19 February 2017 12:58
Memorandum to A. Zaitsev, State Research Centre of Russian Federation Institute for High Energy Physics (IHEP) from K. Long and C. Whyte (as Spokesman and Project Manager) describing briefly the requirements for a cooling demonstration with MICE equipment. The document also indicates possible avenues to collaboration for discussion....
MICE report to the MICE Project Board
28 February 2017 02:05
Report prepared for the April 2017 meeting MICE Project Board.
Response to feedback from the RLSR and MPB
26 April 2017 18:28
Response to feedback from the Resource Loaded Schedule Review panel and the MICE Project Board following their meetings in March 2017.
Request to operate MICE in ISIS User Cycle 2017/03
19 October 2017 14:29
Request to operate MICE in ISIS User Cycle 2017/03
MICE bimonthly project update 8
16 June 2017 14:09
Eighth bimonthly progress report.
Final report to STFC close-out review
09 April 2018 07:44
Report on the MICE experiment to the STFC close-out review that took place on 17 and 18 April 2018.