MEMO Ops 29112016 » History » Version 1
Boyd, Steven, 29 November 2016 13:52
1 | 1 | Boyd, Steven | h3. User cycle : 2016/03 - Nov 15th - Dec 16th |
---|---|---|---|
2 | |||
3 | * MOM : Ed Overton who has (today) handed over to Melissa Uchida. |
||
4 | * MICE is fully staffed (24 hours / day) to the end of the user cycle. |
||
5 | * Been operating since Nov 17th |
||
6 | ** Nov 18 - Nov 23 : LiH materials programme |
||
7 | ** Nov 24 - Nov 28 : Straight track running |
||
8 | ** Nov 29 - : LiH materials + emittance reduction measurements |
||
9 | * Running has been largely smooth. |
||
10 | * Major issues to date : |
||
11 | ** ISIS instability |
||
12 | ** One of the pumps supplying cooling water to the conventional magnets failed leading to continual conventional magnet trips (problem has been understood and mitigation in place, if not fixed) |
||
13 | |||
14 | * Concerns over non-delivery of UK grant and imminent disappearance of expert personnel. |