Operations report¶
- Staffing
- MOMs defined for the next user cycle (but not the one afterwards)
- Shift for the first 4 weeks of the next user cycle
Shift Block ID | # signed up | # shifters still needed |
1 | 6 | 0 |
2 | 4 | 2 |
3 | 4 | 2 |
4 | 4 | 2 |
- BLOCs are being filled
- This is only the first half of the user cycle. We need to consider what we open for
the second half from March 6th - March 31st - 5 shift blocks.
- Operations run-up
- Beam starts on Feb 14 and data-taking on Feb 15.
- We have reserve shift cover from Feb 10 - Feb 14
- Need to define start-up timetable (see Ops meeting)