Actions
2018-06-12-MEMOMIPO¶
Joint MICE Experiment Management Office and MICE International Project Office¶
12th June 2018; 15:30 BST¶
Agenda¶
- Introduction: KL
- Notes of previous meeting and status of actions: All
- PS: Generate two-pager to close-out common fund for next PSAG.
- DR: Continue to push towards a persistence plan for the MICE IIT WWW site.
- DR: Coordinate migration of mail server from IIT to jiscmail.
- Project Manager's report: CW
- Software and computing status: DR
- Paper status and plans: CR
- AOB
Notes¶
Present:
Chris Rogers
Peter Garbinicius
Colin Whyte
Durga Rajaram
- Introduction - KL is in another meeting, CR to chair
- Notes of previous meeting and status of actions: All
- PS: Generate two-pager to close-out common fund for next PSAG.
- No report - stands
- DR: Continue to push towards a persistence plan for the MICE IIT WWW site.
- Purchase order has been placed for webserver at IIT. Static mirror at RAL to be coordinated with Chris Brew.
- DR: Coordinate migration of mail server from IIT to jiscmail.
- KL will migrate EB and CB mailing lists to jiscmail
- CR will migrate analysis mailing list to jiscmail
- DR will migrate software mailing list to jiscmail
- Other mailing lists are inactive and will be archived
- PS: Generate two-pager to close-out common fund for next PSAG.
- Project Manager's report: CW
- See slides
- Since VC
- Tony will go into the synchrotron at next opportunity to check a few survey things
- ISIS have offered resource to help clear MICE hall
- Shipping container for US equipment now expected to arrive w/c 25th June; Alan Br likely to be available in that week
- Software and computing status: DR
- V.Pec has generated a set of new TOF calibrations. TOF bad channel patch has also been brough in. DR running some tests, in time for next release.
- 2017/03 geometry has wrong alignment corrections; fix is in hand.
- Global track matching for backtracking from TKD is now in test. Will not make next release.
- Discussion regarding "cuts" routines; they should be run by default; DR asked CR to check the default values are reasonable
- Handover of computing project
- Archiving mostly done
- Needs some one to manage any data issues and new users (for GRID)
- Durga needs to hand over geometry and "all those things". Some discussion of the details. Action: DR to make a list.
- Paper status and plans: CR
- No update since VC
- AOB
- No AOB
Summary of actions:¶
- PS: Generate two-pager to close-out common fund for next PSAG.
- DR: List the tasks that need to be handed over for software and computing.
Back to MEMO:¶
Back to MIPO:¶
Documents¶
Updated by Rogers, Chris over 5 years ago · 7 revisions