Actions
2018-03-06-MEMOMIPO¶
Joint MICE Experiment Management Office and MICE International Project Office¶
6th March 2018; 15:30 GMT
RAL, R1 2nd Floor East, MICE Meeting room¶
Present: AK, CW, KL, ABr,
- Introduction: KL
- This meeting: revised paper planning; and disscussion of decommissioning.
- Had intended to make a test ramp of the magnets today. This was not possible because Hall was not ready.
- Notes of previous meeting and status of actions: All
- Notes accepted. Status of actions:
- CW: Organise test of QD/QP systems for SSs.
- Ongoing. Tracker removal now complete. PRY completion schedule ramp for next week. CW will circulate the schedule.
- CW: Bracing bars. CW to discuss with JB.
- Done. To be installed but the studing etc. has been agreed.
- CR: Will make list of magnet settings for field mapping exercise.
- Done. A second iteration on the currents will be done by the end of the week.
- CW: Organise test of QD/QP systems for SSs.
- Hall status, stability of systems, planning for decommissioning and making safe to be complete by 31Mar18: CW
- New information is that much of the space in R9 will be lost next week. Need to complete prepration for this.
- Tracker cryostats can be disassembled and scrapped to recover the cryocoolers.
- TOF, EMR, KL all off the beam line. FC off the beamline. Space now an issue and equipment needs to be removed and stored or scrapped.
- Status of preparations for magnetic survey measurements: CW
- CERN mapping team will be here to start work on 19Mar18. Will need to run magnets during week of 19Mar18.
- Preparation of magnet systems next week; CW will issue schedule. Presently believe Tuesday 13Mar18 will be test ramp.
- Will discuss stepping between currents; identified need to minimise ramping time.
- Requests for equipment repatriation: CW
- Now have equipment requests from TOF, KL, EMR, cryos for magnets to US, some other equipment requires to be sent.
- CW: Will draft short document to define repatriation.
- Software and computing status: DR
- No report this week.
- Paper status and plans: CR
- See table uploaded: 2018-03-05-Papers-in-progress-v1.pdf . Points noted:
- Emittance paper: systematic uncertainties and data MC comparison are remaining issues.
- LiH scattering: Asymmetry in scattering distribution principle issue.
- Emittance evolution: Working through details of systematics.
- Emittance exchange: Now need to study beam selection and limiting appertures.
- Other papers: see table; clear goals for completion of many papers. Papers on field-on scattering etc. need to progress before completion dates can be defined.
- See table uploaded: 2018-03-05-Papers-in-progress-v1.pdf . Points noted:
- AOB
- None.
Summary of actions:¶
- CW: Organise test of QD/QP systems for SSs.
- CW: Will draft short document to define repatriation.
Back to MEMO:¶
Back to MIPO:¶
Documents¶
Updated by Long, Kenneth over 5 years ago · 3 revisions