h2. Joint MICE Experiment Management Office and MICE International Project Office
4
5
h3. 06th February 2018; 15:30 GMT
6
*RAL, R1 2nd Floor East, MICE Meeting room*
7
8
"Phone details":http://mice.iit.edu/phonebridge.html
9
10
# *Introduction: KL*
11
# *Notes of previous meeting and status of actions: All*
12
** *CW:* Organise test of QD/QP systems for SSs.
13 4 Whyte, Colin
*** CMcW and JB to check this week. - no config files.
14
*** SSU at 3T and match coils - nominal settings
15
*** SSD 3T and then 2T.
16
*** Action CW - bracing bars. CW to discuss with JB.
17 1 Long, Kenneth
** *KL:* Contact supervisor of CERN field-mapping team to seek to secure permission for them to carry out the MICE magnetic-field survey.
18 4 Whyte, Colin
*** complete agreed on week of 19th March
19 1 Long, Kenneth
** *KL/CW:*  Issue first version of the decommissioning plan this week.
20 4 Whyte, Colin
*** completed today.
21 1 Long, Kenneth
# *Hall status, stability of systems, planning for decommissioning and making safe to be complete by 31Mar18: CW*
22 4 Whyte, Colin
*** Move out R9 to Hall
23
*** Quads, Tof2 KL, EMR.
24
*** Action CW to contact Oxford Machine shop re-diffuser.
25
*** FC pressure - helium pressure 1160mbar - cryo mech 340/310psi - high ambient pressure. Leave until Mon 11th.
26
*** SSD pressure increase next week.
27
*** US DoE
28
**** Mu2E QPS system
29
**** cryocoolers and compressors - Mu2E - request is from institution - not approved at higher level. 
30
**** MP to raise with DoE
31 1 Long, Kenneth
# *Data validation ahead of start of Cycle 2017/04: CR*
32 3 Rogers, Chris
** [[analysis:2018-02-01_no-run_summary|Summary of studies of data validity]]
33 1 Long, Kenneth
# *Software and computing status: DR*
34 4 Whyte, Colin
** issues on processing time - run on RAL PPD grid. Making changes with Chris Brew - should be on line by next week.
35
** memory issues solved
36
** some geometry issues - DR working to solve. Most recent survey was before wedge change.
37
** tracker and ToF meetings still to be scheduled
38
** computing infrastructure inventory in progress.
39 1 Long, Kenneth
# *Memo on measurements required before experiment is decommissioned: CR*
40 2 Rogers, Chris
** No update
41 1 Long, Kenneth
# *Paper status and plans: CR*
42 4 Whyte, Colin
** meetings last week
43
*** scattering straight tracks steady progress - refs meeting at CM
44
*** VB no progress report - ready for CM
45
*** CR plan to be ready for CM50
46 1 Long, Kenneth
# *AOB*