2015-11-17 memo-operations-report » History » Version 8
Boyd, Steven, 17 November 2015 14:42
1 | 1 | Boyd, Steven | h1. 2015-11-17 memo-operations-report |
---|---|---|---|
2 | |||
3 | h1. 2015/03 |
||
4 | |||
5 | 6 | Boyd, Steven | * Weekly commissioning scheduling meetings started. First one worked well - let's see how it develops. Next meeting @ 15:30 today |
6 | 2 | Boyd, Steven | * Activities this week can be seen in the weekly work plan at the top of the Operations page. |
7 | 1 | Boyd, Steven | * 3 shift blocks assigned for end of the current user cycle. Not well populated yet. We will have to see |
8 | what the take-up is before we define the running mode (24/16 hour?) |
||
9 | * November 24th will be an expert led run. Ed is leading this. |
||
10 | * Recent activation run has been analysed and shows significant activation of some sections of ISIS. Dean |
||
11 | is wary about 4V beamloss running but will try to maximise our event rate through other means. Apparently |
||
12 | 8 | Boyd, Steven | activation runs are no longer necessary - they will monitor as we take data at the start and end of user cycles and during maintenance days. |
13 | 1 | Boyd, Steven | * Ed/Durga are looking into online code version documentation (in accordance with MPB recommendations) |
14 | 7 | Boyd, Steven | * In the process of putting in place a procedure for change control (essentially an online form with change authorised by MOM) |