2015-01-15-MEMO-CSw-Status » History » Version 1

Rajaram, Durga, 15 January 2015 12:58

1 1 Rajaram, Durga
h1. 2015-01-15-MEMO-CSw-Status
2
3
h2. Offline
4
5
* Updates to batch reconstruction scripts for reprocessing with different configuration cards
6
** Should be in next MAUS release. PID paper reprocessing is pending this
7
* Global tracking revamp in progress using Runge Kutta instead of transfer maps
8
** expecting first results by CM41
9
* Priority Items: 
10
** fix broken tracker unpacking
11
** fix to salvage "corrupt data" from old runs -- affects PID paper
12
** add reconstruction quality flags
13
* Tracker and MAUS papers in circulation
14
** awaiting updates to EMR, Ckov, and Global sections for MAUS paper
15
** Global group has promised by CM41
16
17
h2. Online
18
19
* MLCR network switch replaced
20
* Continuing identification of backup needs and requirements for spares/replacements
21
* On-call rota: filling up roster, need more volunteers
22
* Found data corruption in some older runs
23
** Yordan attempting a fix to salvage already corrupt data
24
** Need to make sure we catch such issues earlier, pre-reconstruction so that  we don't take corrupted data
25
26
h2. Infrastructure
27
28
* Preparing for MC batch production
29
** necessary scripts are in latest offline release, testing CDB production tables, and beam-input bureaucracy 
30
* DataMover automation plan to test by the next activation run
31
32
* heplnm069 replacement: delivery pending
33
* Plans to migrate offline test server and epics gateways to HyperV
34
* Warwick postdoc slated to take charge of Infrastructure from Jan 15. 
35
36
h2. Schedule & Milestones
37
38
* Will be working with Roy Preece on getting C/Sw schedule into MS Project & identifying milestones to report/track
39
40
h2. Controls & Monitoring
41
42
* cf.  Pierrick Hanlet's report