Project

General

Profile

Geometry release procedure » History » Version 1

Rogers, Chris, 09 January 2012 12:18

1 1 Rogers, Chris
h1. Geometry release procedure
2
3
A new geometry will be released when there is a new survey performed in the hall. The procedure is as follows:
4
5
| Process | Responsible |
6
| New geometry is released as a set of gdml files - email sent to Chris Rogers and Matt Littlefield | Jason Tarrant |
7
| New geometry is uploaded to configuration database | Matt Littlefield (or Chris Rogers) |
8
| Geometry test period is announced | Matt Littlefield (or Chris Rogers) |
9
| Geometry testing | System experts (listed below) |
10
| Geometry released | Matt Littlefield (or Chris Rogers) |