A new geometry will be released when there is a new survey performed in the hall. The procedure is as follows:

Process Responsible
1 New geometry is released as a set of gdml files - email sent to Stefania Ricciardi and Ryan Bayes Jason Tarrant
2 New geometry is uploaded to preprod configuration database Ryan Bayes (or Stefania Ricciardi)
2.1 Run a test job on the test server Ryan Bayes (or Stefania Ricciardi)
2.2 Upload geometry validation plots to wiki page Ryan Bayes (or Stefania Ricciardi)
3 Assuming tests pass, upload geometry to the production CDB Ryan Bayes (or Stefania Ricciardi)

The usual system experts are:

System Responsible
Beamline Adam Dobbs
TOF Durga Rajaram
EMR Ruslan Asfandiyarov
Ckov Lucien Cremaldi
Tracker Chris Heidt
KL Mariyan Bogomilov
Cooling Channel Analysis Group c/o Victoria Blackmore

Updated by Rogers, Chris over 8 years ago ยท 14 revisions