2016-07-25-MagnetMeeting

RAL R1 15.00UK, 09.00Chicago

Phone : Readytalk- http://mice.iit.edu/phonebridge.html

Agenda

  • Introduction:
  • Notes of last meeting and actions:
    • All outstanding actions (SF) parked until end of month.
  • Update on last day's running on Wed 20th July 2016 - CMcW.

Analysis group input

Technical discussion

  • FC - SS forces (single SS)?
    • measurable? _ Actions to fix?
  • FC thermal performance
    • What should current steps be?
    • How long at each current setting? ( 1 hour?)
  • Ramp rates & quenches:
    • Will an SS quench cause the FC to quench? (Yes, demonstrated )
    • Will an FC quench cause the SS's to quench? (Probably)
    • Will fast rundown of an SS cause the FC to quench (No)
    • What FC ramp rate will trip the SS QP system? (Probably > 25 mA/sec
      but requires study/measurement.)
    • Does 'canonical' 25mA/sec ramp of SSs cause FC QP to trip (No)
  • Status of fast FC data logger
  • 'Standoffs' between SSx and PRY end plates - PRY/Magnet movement - CW/JT

Discussion of next steps

Plan for Monday 18th July

  • DONM
  • AoB