MICE Project Board and Resource Loaded Schedule Review, April 2015¶
Documentation¶
- RLSR:
- "Resource loaded schedule, costs and risks for the completion of the MICE project":
- Supporting documents:
- Response to feedback from the RLSR panel and the MPB
- MICE-US project Gantt chart: 15-04-03-MAP-RampDown.pdf
- MICE-US milestone waterfall chart: 15-04-03-MAP-RampDown-GanttChart-Milestones.pdf
- MICE-US MS project file: 15-04-03-MAP-RampDown.mpp
- MICE-US risk register: MAP_RevisedRiskRegister_ExpeditedPlan_2015_0406.xlsx
RLSR, MPB & FAC outline agendas – 16 & 17 April 2015¶
Venue: Conference Room 21, Building R1, RAL
Thursday, 16 April 2015 and Friday, 17 April 2015¶
RLSR & MPB-9 outline agendas¶
16 April 2015 | |||
09:00-09:45 | RLSR closed session – introduction | ||
09:45-10:15 | Project overview: 01-2015-04-16-Long.pptx | K. Long | 20' + 10' |
10:15-12:45 | RLSR presentations & questions | ||
Schedule to completion, project risks and overview of critical interfaces: 02-2015-04-16-Preece.ppt | R. Preece | 30' + 10' | |
Re-baselined deliverables, critical decision points and status of US deliverables: attachment:03_Palmer_RLSR_R2.pptx | M. Palmer | 30' + 10' | |
UK financial plan, risks: 04-Slides-grant-2015-4-16_RLSR.pptx | A. Grant | 20' + 10' | |
US financial plan, risks: 05-April-2015-US-Project-Plan.pptx | P. Garbincius | 20' + 10' | |
Unscheduled | 150’ - 140’ | = 05' | |
12:45-13:15 | Lunch | ||
13:15-14:00 | RLSR closed session – critical findings | ||
14:00-15:30 | Step IV, commissioning, operations and control | ||
Step IV commissioning and operations planning; overview: attachment:06-Operations_MPBTalk_Apr2015_Draft_v3.pdf | S. Boyd | 20' + 5' | |
MICE Muon Beam and MICE channel optics and commissioning plan | J. Pasternak | 15' + 5' | |
Step IV measurements and analysis planning: 08-Step-IV-Analysis.pdf | C. Rogers | 15' + 5' | |
Controls and monitoring: attachment:mpbSp15_hanlet_v2.pdf | P. Hanlet | 15' + 5' | |
Unscheduled | 90’ - 85’ | = 5' | |
15:30-16:00 | Closed session | ||
16:00-17:30 | Reconstruction, simulation and data flow | ||
Software, computing and data processing; overview: 10-computing-mpb-apr2015.pdf | D. Rajaram | 15' + 5' | |
Reconstruction; online, offline and batch: attachment:11-MAUS-Update-v4.pptx | A. Dobbs | 15' + 5' | |
Simulation and configuration management: 12-SimulationConfigurationManagement.pdf | R. Bayes | 10' + 5' | |
Data flow: from front-end boards to automatic batch processing: attachment:Online_Report_YK.pdf | Y. Karadzhov | 10' + 5' | |
MICE computing infrastructure: 14-Franchini_MPBApril2015_infrastructure.pdf | P. Franchini | 10' + 5' | |
Unscheduled | 90’ - 85’ | = 5' | |
17:30-18:00 | Closed session, report writing | ||
18:00 | Adjourn | ||
17 April 2015 | |||
09:00-10:30 | Cooling-demonstration integration, SC magnets and RF | ||
Focus-coils, absorbers and LH2 system for Step IV: 15-MPB_18-04-15_AFC_LH2.ppt | S. Watson | 20' + 10' | |
Cavity modules and test programme, PRY and spectrometer solenoids: attachment:16-MPB_4-15_v1.pptx | A. Bross | 20' + 10' | |
RF-power distribution: attachment:17-RF_Status_Update-5-Apr-2015.pptx | K. Ronald | 20' + 10' | |
Unscheduled | 90’ - 90’ | = 0' | |
10:30-11:30 | Closed session, report writing | ||
11:30-12:00 | Close-out with MICE management | ||
12:00-13:00 | Lunch | ||
13:00 | Adjourn for report writing |