MICE Project Board and Resource Loaded Schedule Review, April 2015¶
Documentation¶
- RLSR:
- "Resource loaded schedule, costs and risks for the completion of the MICE project":
- Supporting documents:
- Response to feedback from the RLSR panel and the MPB
- MICE-US project Gantt chart: 15-04-03-MAP-RampDown.pdf
- MICE-US milestone waterfall chart: 15-04-03-MAP-RampDown-GanttChart-Milestones.pdf
- MICE-US MS project file: 15-04-03-MAP-RampDown.mpp
- MICE-US risk register: MAP_RevisedRiskRegister_ExpeditedPlan_2015_0406.xlsx
RLSR, MPB & FAC outline agendas – 16 & 17 April 2015¶
Venue
Thursday, 16 April 2015 and Friday, 17 April 2015¶
RLSR & MPB-9 outline agendas¶
16 April 2015 | |||
09:00-09:45 | RLSR closed session – introduction | ||
09:45-10:15 | Project overview | K. Long | 20' + 10' |
10:15-12:45 | RLSR presentations & questions | ||
Schedule to completion, project risks and overview of critical interfaces | R. Preece | 30' + 10' | |
Re-baselined deliverables, critical decision points and status of US deliverables | M. Palmer | 30' + 10' | |
UK financial plan, risks | A. Grant | 20' + 10' | |
US financial plan, risks | P. Garbincius | 20' + 10' | |
Unscheduled | 150’ - 140’ | = 05' | |
12:45-13:15 | Lunch | ||
13:15-14:00 | RLSR closed session – critical findings | ||
14:00-15:30 | Step IV, commissioning, operations and control | ||
Step IV commissioning and operations planning; overview | S. Boyd | 20' + 5' | |
MICE Muon Beam and MICE channel optics and commissioning plan | J. Pasternak | 15' + 5' | |
Step IV measurements and analysis planning | C. Rogers | 15' + 5' | |
Controls and monitoring | P. Hanlet | 15' + 5' | |
Unscheduled | 90’ - 85’ | = 5' | |
15:30-16:00 | Closed session | ||
16:00-17:30 | Reconstruction, simulation and data flow | ||
Software, computing and data processing; overview | D. Rajaram | 15' + 5' | |
Reconstruction; online, offline and batch | A. Dobbs | 15' + 5' | |
Simulation and configuration management | R. Bayes | 10' + 5' | |
Data flow: from front-end boards to automatic batch processing | Y. Karadzhov | 10' + 5' | |
MICE computing infrastructure:http://micewww.pp.rl.ac.uk/attachments/3730/Franchini_MPBApril2015_infrastructure.pdf | P. Franchini | 10' + 5' | |
Unscheduled | 90’ - 85’ | = 5' | |
17:30-18:00 | Closed session, report writing | ||
18:00 | Adjourn | ||
17 April 2015 | |||
09:00-10:30 | Cooling-demonstration integration, SC magnets and RF | ||
Focus-coils, absorbers and LH2 system for Step IV | S. Watson | 20' + 10' | |
Cavity modules and test programme, PRY and spectrometer solenoids | A. Bross | 20' + 10' | |
RF-power distribution | K. Ronald | 20' + 10' | |
Unscheduled | 90’ - 90’ | = 0' | |
10:30-11:30 | Closed session, report writing | ||
11:30-12:00 | Close-out with MICE management | ||
12:00-13:00 | Lunch | ||
13:00 | Adjourn for report writing |
Backup presentations:¶
- To be posted.