2015-04-16-Review » History » Revision 1

Revision 1/52 | Next »
Long, Kenneth, 17 March 2015 08:55


2015-04-16-Review

Agendas and supporting material for:
  • Resource Loaded Schedule Review 5
  • MICE Project Board 8
  • FAC

RLSR, MPB & FAC outline agendas – 16 & 17 April 2015
Venue

Thursday, 16 April 2015

RLSR & MPB-8 outline agendas
16 April 2015
09:00-09:45 RLSR closed session – introduction
Project overview K. Long ??' + ??'
:??-:?? RLSR presentations & questions
Schedule to completion and project risks R. Preece ??' + ??'
US project plan for MICE M. Palmer ??' + ??'
UK financial plan, risks A. Grant ??' + ??'
Unscheduled ?’ - ? = ??'
12:45-13:15 Lunch
13:15-??:?? RLSR closed session – critical findings
:??-:?? Step IV, commissioning, operations and control
Step IV commissioning and operations planning; overview S. Boyd ??' + ??'
MICE Muon Beam and MICE channel optics and commissioning plan J. Pasternak ??' + ??'
Step IV measurements and analysis planning C. Rogers ??' + ??'
Controls and monitoring P. Hanlet ??' + ??'
Unscheduled ?’ - ? = ??'
15:30-??:?? Closed session, report writing
16:00-??:?? Reconstruction, simulation and data flow
Softwre, computing and data processing; overview D. Rajaram ??' + ??'
Reconstruction; online, offline and batch A. Dobbs ??' + ??'
Simulation and configuration management R. Bayes ??' + ??'
Data flow: from front-end boards to automatic batch processing Y. Karadzhov ??' + ??'
Unscheduled ?’ - ? = ??'
17:30-18:00 Closed session, report writing
18:00 Adjourn

Tuesday November 25th

MPB-8 outline agenda
  • 9:00-10:30 Commissioning, operations & control
    • 09:00-09:35 Commissioning and operations overview — S. Boyd: 25’ + 10’
      • attachment:11-MPBTalk_Ops.pdf
    • 09:35-09:50 MICE/ISIS liaison, the ISIS perspective — S. Wakefield: 10’ + 5’
      • attachment:12-MICE_ISIS_interactions.pptx
    • 09:50-10:20 Controls and monitoring — P. Hanlet: 20’ + 10’
      • attachment:13-mpbFa14_hanlet.pdf
    • 10:20-10:30 Unscheduled 90’ - 80’ = 10'
  • 10:30-11:30 Closed session, report writing
  • 11:30-12:00 Close-out with MICE management
  • 12:00-13:00 Lunch
  • 13:00 Adjourn for report writing
FAC outline agenda
  • 15:30-15_40 Minutes of the last meeting including Actions and Matters Arising
  • 15:40-16:00 Progress since the last FAC meeting and DOE review, Key Issues and Concerns: Ken Long
    • attachment:01-2014-11-25-Long.pptx
  • 16:00-16:20 Schedule & Milestones: Roy Preece
    • attachment:02-2014-11-25-FAC-Preece.ppt
  • 16:20-16:40 Resource Loaded Schedule Review: Ian Robson
  • 16:40-17:00 MPB Recommendations: Steve Peggs
  • 17:00-17:20 Funding Status (Statement from each representative)
  • 17:20-17:30 Common Fund: Paul Soler
    • attachment:05-MICE_CF_FAC_Nov2014.pptx
  • 17:30- Any other business

Backup presentations:

  • J. Pasternak: Magnet and beamline commissioning:
    • attachment:Magnet_and_Beam_Commissioning_at_StepIV_MPB_112014.pdf
  • C. Rogers: MICE cooling demonstration configuration:
    • attachment:rogers_cooling-demo_mpb.pdf

Documentation

  • Single PDF containing all files:
    • Concatenated pdf: attachment:00-2014-11-11-All-files.pdf