Project

General

Profile

Actions

2014-11-24-Review » History » Revision 8

« Previous | Revision 8/48 (diff) | Next »
Long, Kenneth, 10 November 2014 21:22


2014-11-24-Review

Documentation

  • Response to feedback:
    • Resource loaded schedule, costs and risks for the completion of the MICE project
      • Supporting documents:
        • The MICE Demonstration of Ionisation Cooling: Technical Note: attachment:MICE-Demonstration-Of-Ionisation-Cooling.pdf
        • Assumptions Document: attachment:2014-10-27-Assumptions-doc.pdf
        • Documentation of prioritised controls plan: attachment:
        • Online support plan: attachment:
        • Magnet commissioning at Step IV: attachment:
        • Commissioning and operations at Step IV: attachment:
        • RF test plan document: attachment:
        • Initial consideration of the running required for the demonstration of ionization cooling: attachment:
    • Initial response (July 2014): attachment:2014-07-25-ResponseToFeedback.pdf
  • MPB:
    • Status report:
      • PDF: attachment:MPB-report.pdf
      • Tar ball: attachment:MPB-report.tar.gz
      • PDF: attachment:MPB-report-v2.pdf
      • Tar ball: attachment:MPB-report-v2.zip

Back

Updated by Long, Kenneth over 8 years ago · 8 revisions