3 | 5 | Long, Kenneth | h2. Documentation |
4 | 1 | Long, Kenneth | |
5 | * RLSR: |
||
6 | 6 | Long, Kenneth | ** "Resource loaded schedule, costs and risks for the completion of the MICE project":http://micewww.pp.rl.ac.uk/attachments/2885/2014-11-10-RLSR-report.pdf |
7 | 1 | Long, Kenneth | |
8 | * Response to feedback: |
||
9 | 8 | Long, Kenneth | ** "Resource loaded schedule, costs and risks for the completion of the MICE project":http://micewww.pp.rl.ac.uk/attachments/2888/2014-11-10-ResponseToFeedback.pdf |
10 | 9 | Long, Kenneth | |
11 | * Supporting documents: |
||
12 | ** "The MICE Demonstration of Ionisation Cooling: Technical Note":http://mice.iit.edu/micenotes/public/pdf/MICE0452/MICE0452.pdf |
||
13 | 23 | Long, Kenneth | ** "MICE Assumptions Document":http://micewww.pp.rl.ac.uk/attachments/2892/2014-11-10-Assumptions-doc.pdf |
14 | 11 | Long, Kenneth | ** "Documentation of prioritised controls plan":http://micewww.pp.rl.ac.uk/attachments/2882/Controls_System_Priotitised_Plan_v5.pdf |
15 | 12 | Long, Kenneth | ** "Online support plan":http://micewww.pp.rl.ac.uk/attachments/2870/On_Call_Responsibilities_V05.pdf |
16 | 22 | Long, Kenneth | ** "Magnet commissioning at Step IV":http://micewww.pp.rl.ac.uk/attachments/2891/2014-11-10-Magnet_and_Beam_Commissioning.pdf |
17 | 13 | Long, Kenneth | ** "Commissioning and operations at Step IV":http://micewww.pp.rl.ac.uk/attachments/2884/2014-11-10-Step-IV-Commissioning-n-Operations.pdf |
18 | 20 | Long, Kenneth | ** "RF test plan and consideration of commissioning of ionization cooling demonstration":http://micewww.pp.rl.ac.uk/attachments/2890/2014-11-10-ICD-test-n-commission.pdf |
19 | 15 | Long, Kenneth | ** "Initial consideration of the running required for the demonstration of ionization cooling":http://micewww.pp.rl.ac.uk/attachments/2886/2014-11-10-ICD-initial-ops-plan.pdf |
20 | 17 | Long, Kenneth | ** Response to recommendations of DOE August 2014 review of MAP and MICE: attachment:DOE_Response_2014_0925_FINAL.pdf |
21 | 16 | Long, Kenneth | ** "Initial response (July 2014) to recommendations":http://micewww.pp.rl.ac.uk/attachments/2346/2014-07-25-ResponseToFeedback.pdf |
22 | 1 | Long, Kenneth | |
23 | * MPB: |
||
24 | ** Status report: |
||