h2.Documentation

  • Response to feedback:
    • Initial response (July 2014): attachment:2014-07-25-ResponseToFeedback.pdf
    • Response to feedback (draft): attachment:ResponseToFeedback.pdf
      • Supporting documents:
        • The MICE Demonstration of Ionisation Cooling: Technical Note: attachment:MICE-Demonstration-Of-Ionisation-Cooling.pdf
        • Assumptions Document: attachment:2014-10-27-Assumptions-doc.pdf
        • Documentation of prioritised controls plan: attachment:
        • Magnet commissioning at Step IV: attachment:
        • Commissioning and operations at Step IV: attachment:
        • RF test plan document: attachment:
        • Initial consideration of the running required for the demonstration of ionization cooling: attachment:
  • RLSR:
    • RLSR report (draft): attachment:RLSR-report.pdf
  • MPB:
    • Status report: attachment:MPB-report.pdf