2014-03-18-MEMO

MICE Experiment Management Office

18th March 2014; 14:00 GMT

Phone details

Back

  1. Introduction: KL
  2. Notes on previous meeting, status of actions: All
  3. Report/actions from MIPO PH
  4. Status reports:
    1. Operations: SB
    2. Physics: VB
    3. S/w&C: CR
  5. Operations plan Jan to Jun, first cut: SB/All
    • 04—06Apr14: 0.8Hz and DAQ commissioning;
      • OK if we have DKsol, D2, proton absorber and DAQ and block-test done;
      • One shift’s worth of running;
      • Plan as expert-only activity;
      • MOM team writes MICE Note on results;
    • 29—30Jun14: 0.8Hz activation run:
      • 16-hour run with MICE experiment; 16-hours rest, then survey;
      • Plan as MICE test run;
  6. Papers for RLSR and MPB: KL
  7. DONM
    • 01Apr14; 14:00 GMT;
  8. AoB