h1. Feb2015 


 # Find location of RK in sw - Melissa Jan - DONE 
 # **    Output DS track without going through primary and hack in KL event from the same spill assuming it is with a track if from the same spill to Celeste for PID - Jan    - DONE 
 # ** #** Help Jan by writing KL importer - Celeste    - DONE 
 # ** #** Do the above using the RK on Tracker TOF2 and KL - Jan    - DONE 
 # ** #** Do DS PID on hacked track - Celeste    - DONE 
 # ** #** Calculate DS track efficiency based on point 4. - Celeste - IMPROVE 
 # ** #** Calculate DS track Pt based on MC to test new cuts. - Celeste - DONE 
 # ** #** Calculate DS track Pt based on point 5. - Celeste - IMPROVE 
 # ** #** Determine how to do track finding efficiency, with a clear plan any number possible determine them by cm 41 - Jan - IMPROVE 
 # Fix #Fix the seg fault    - Jan, Chris, Melissa 
 # Person #Person responsible KL software - Melissa - DONE    John N and in charge Mariyan Bogomilov, Mariyan.Bogomilov@cern.ch 
 # KL #KL hardware responsible - Melissa - DONE    Ludovico Tortora 
 # Is #Is KL y position limit hardware or software based? - Melissa - DONE 
 #** Rehash collab meeting schedule to make it a 5 min intro from me followed by 15 minutes Jan track matching, 15 minutes Celeste plus 5 minutes on analysis - Melissa to ask Chris - DONE 
 #** Write outline for CM41 15 minute talks - Jan and Celeste - DONE 
 #Understand EMR keep talking to Francoise - Celeste - IMPROVE 
 #* Through going tracks from TOF1 to TOF 2 done add in KL (and eventually EMR when above is completed) - Celeste 
 #* Through going tracks from TOF1 to TOF 2 inc KL (and eventually EMR when above is completed) - Jan 
 #Add energy loss to RK - Melissa Jan 
 #Make MICE Mine page - Melissa - DONE  

 ** Pre cm41 
 * If poss pre cm41 

 # Documenatation