1 2 Preece, Roy
h1. Drawings for discussion and approval
2
3 10 Preece, Roy
_*Drawing files posted in this area are for discussion in meetings leading to approval. Once approved the drawings will be posted in the issue area of the Electrical Wiki. Drawing files will be removed from this area when superseded or issued.*_
4 3 Preece, Roy
5
h2. Infrastructure Meeting 7th January 2015
6
7
Tray/trunking layout drawing which show the proposed changes to the trunking for the vacuum cables on the south side of the hall.
8 6 Preece, Roy
** attachment:204-70025_3.pdf
9 8 Preece, Roy
** attachment:204-70025_10.pdf
10
** attachment:204-70025_11.pdf
11 5 Preece, Roy
12 1 Rogers, Chris
Proposed Spectrometer Solenoid Chilled water system for the Energy Dump trays.
13 8 Preece, Roy
** attachment:Chilled_Water_System.pdf
14
15 7 Preece, Roy
16
h2. Uploaded Files