1 | 2 | Rogers, Chris | h1. DOE Reviews |
---|---|---|---|
2 | 3 | Long, Kenneth | |
3 | h2. DOE review of MAP and MICE, Brookhaven National Laboratory, 12th to 14th August 2014 |
||
4 | 4 | Long, Kenneth | |
5 | h3. Documents: |
||
6 | |||
7 | 23 | Long, Kenneth | # *document#95* |
8 | 14 | Long, Kenneth | ** +To do:+ |
9 | ### *US Proj. Off.:* Sign-off from US project team |
||
10 | 4 | Long, Kenneth | ** +Figures:+ |
11 | 8 | Long, Kenneth | ### Step IV Dashboard: attachment:Figure-1-MICE_Dashboard.pdf |
12 | 6 | Long, Kenneth | ### Step IV baseline schedule milestones: attachment:Figure-2-Step_IV_milestones_Waterfall.pdf |
13 | ### Step V critical path relating to Plan A: attachment:Figure-3-StepV_Critical_Path_Advanced.pdf |
||
14 | ### Step V critical path relating to Plan B: attachment:Figure-4-StepV_Critical_Path_Flat_Funding.pdf |
||
15 | 11 | Long, Kenneth | ### Spend profile required to carry complete Step V according to Plan A: attachment:Figure-5-Advanced-UK-US_Finance.pdf |
16 | ### Spend profile required to carry complete Step V according to Plan B: attachment:Figure-6-Flat_UK-Flat_US-UK-US_Finance.pdf |
||
17 | 4 | Long, Kenneth | ** +Tables:+ |
18 | 7 | Long, Kenneth | ### Interface points identified in the MICE baseline-schedule analysis: attachment:Table-1-Delivered_Required_Dates.pdf |
19 | ### Step IV baseline critical path: attachment:Table-2-Step_IV_Critical-Imminent-Near.pdf |
||
20 | ### The tasks which lie on the Step~V baseline critical path for Plan A: attachment:Table-3-StepV_Critical_Near_Advanced.pdf |
||
21 | ### The tasks which lie on the Step~V baseline critical path for Plan B: attachment:Table-4-StepV_Critical_Near_Flat.pdf |
||
22 | 11 | Long, Kenneth | ### The UK requirement for the completion of Step V according to Plan A: attachment:Table-5-UK-Advanced_Spend_profile.pdf |
23 | ### The UK requirement for the completion of Step V according to Plan B: attachment:Table-6-UK-Flat_funded_Spend_profile.pdf |
||
24 | ### The UK requirement for the completion of MICE at Step IV: attachment:Table-7-UK-Stop_Step_IV_Spend_profile.pdf |
||
25 | 12 | Long, Kenneth | ### Top level risks for the sub-projects for which the UK is responsible: attachment:Table-8-STFC-RiskRegisterAug.pdf |
26 | 22 | Long, Kenneth | ### Top level risks for the sub-projects for which the US is responsible: attachment:Table-9-MAP-RiskRegister.pdf |
27 | 12 | Long, Kenneth | ### Risk history for US risks: attachment:Table-10-US-risk_history.pdf |
28 | 19 | Long, Kenneth | # *document#94* |
29 | 13 | Long, Kenneth | # *_DRAFT:_* *MICE Project Assumptions Document*: attachment:Assumptions-doc.pdf |
30 | ** +To do:+ |
||
31 | ### *KL/RP:* make final update for this issue on Monday 04Aug14. |
||
32 | 15 | Long, Kenneth | # *_DRAFT:_* *Planning the MICE Step IV Data Campaign*: attachment:DataPlan.pdf |
33 | 1 | Rogers, Chris | ** +To do:+ |
34 | ### *SB/VB:* make final update for on Monday 04Aug14. |
||
35 | 21 | Long, Kenneth | # *_DRAFT:_* *MICE Step IV magnet and beamline commissioning plan*: attachment:Magnet_and_Beam_Commissioning.pdf |
36 | 16 | Long, Kenneth | ** +To do:+ |
37 | ### *JPa/KL:* make final update for on Monday 04Aug14. |
||
38 | # *_DRAFT:_* *MICE Step IV instrumentation commissioning plan*: attachment:InstrPlan.pdf |
||
39 | ** +To do:+ |
||
40 | ### *PS:* make final update for on Monday 04Aug14. |
||