Long, Kenneth, 03 August 2014 12:12
DOE Reviews¶
DOE review of MAP and MICE, Brookhaven National Laboratory, 12th to 14th August 2014¶
Documents:¶
- DRAFT: Status of the MICE Project: attachment:DOE-Review-MICE-Status.pdf
- To do:
- Update US risk tables;
- Sign-off from US project team
- Figures:
- Step IV Dashboard: attachment:Figure-1-MICE_Dashboard.pdf
- Step IV baseline schedule milestones: attachment:Figure-2-Step_IV_milestones_Waterfall.pdf
- Step V critical path relating to Plan A: attachment:Figure-3-StepV_Critical_Path_Advanced.pdf
- Step V critical path relating to Plan B: attachment:Figure-4-StepV_Critical_Path_Flat_Funding.pdf
- Spend profile required to carry complete Step V according to Plan A: attachment:Figure-5-Advanced-UK-US_Finance.pdf
- Spend profile required to carry complete Step V according to Plan B: attachment:Figure-6-Flat_UK-Flat_US-UK-US_Finance.pdf
- Tables:
- Interface points identified in the MICE baseline-schedule analysis: attachment:Table-1-Delivered_Required_Dates.pdf
- Step IV baseline critical path: attachment:Table-2-Step_IV_Critical-Imminent-Near.pdf
- The tasks which lie on the Step~V baseline critical path for Plan A: attachment:Table-3-StepV_Critical_Near_Advanced.pdf
- The tasks which lie on the Step~V baseline critical path for Plan B: attachment:Table-4-StepV_Critical_Near_Flat.pdf
- The UK requirement for the completion of Step V according to Plan A: attachment:Table-5-UK-Advanced_Spend_profile.pdf
- The UK requirement for the completion of Step V according to Plan B: attachment:Table-6-UK-Flat_funded_Spend_profile.pdf
- The UK requirement for the completion of MICE at Step IV: attachment:Table-7-UK-Stop_Step_IV_Spend_profile.pdf
- To do:
Updated by Long, Kenneth about 9 years ago · 11 revisions