Tunnell, Christopher, 10 November 2011 15:10

1 2 Rogers, Chris
h1. Online Reconstruction Setup - PC 10/11/2011 - Chris Rogers
2 1 Rogers, Chris
3 8 Tunnell, Christopher
For the running we hope to mimic the TOF functionality that was available in G4MICE in MAUS
4 1 Rogers, Chris
5
Status:
6 2 Rogers, Chris
* Online recon in G4MICE has been observed to work and make plots. 
7 1 Rogers, Chris
** Unfortunately there was some problem with the DAQ so I could see no data in either DAQ monitoring or the G4MICE monitoring. 
8
* We still need to write the (small) piece of code that pulls the relevant data from the TOF reconstruction stream
9 7 Rogers, Chris
** Phone call with Durga + Yordan on Friday to discuss who does this
10 1 Rogers, Chris
* We still need to install MAUS on the OnRec machines. 
11
** We have installed on a mimic test machine of the control room machines and checked everything works okay.
12
** We are waiting for an OS upgrade of the relevant machines before doing the install on the OnRec machines.
13 4 Rogers, Chris
* Conversation with Linda => we will spend some time with beam before the main running period to make sure this works.
14
** Combining with target test potentially
15 5 Rogers, Chris
16
17 2 Rogers, Chris
I will reserve the week 21-25 November to make sure that this stuff all glues together properly.