PC 101111 online rec » History » Version 5
Rogers, Chris, 10 November 2011 14:36
1 | 2 | Rogers, Chris | h1. Online Reconstruction Setup - PC 10/11/2011 - Chris Rogers |
---|---|---|---|
2 | 1 | Rogers, Chris | |
3 | For the running we hope to mimic the TOF functionality that was available in G4MICE, except phase space plots will not be available |
||
4 | |||
5 | Status: |
||
6 | 2 | Rogers, Chris | * Online recon in G4MICE has been observed to work and make plots. |
7 | 1 | Rogers, Chris | ** Unfortunately there was some problem with the DAQ so I could see no data in either DAQ monitoring or the G4MICE monitoring. |
8 | * We still need to write the (small) piece of code that pulls the relevant data from the TOF reconstruction stream |
||
9 | * We still need to install MAUS on the OnRec machines. |
||
10 | ** We have installed on a mimic test machine of the control room machines and checked everything works okay. |
||
11 | ** We are waiting for an OS upgrade of the relevant machines before doing the install on the OnRec machines. |
||
12 | 4 | Rogers, Chris | * Conversation with Linda => we will spend some time with beam before the main running period to make sure this works. |
13 | ** Combining with target test potentially |
||
14 | 5 | Rogers, Chris | |
15 | |||
16 | 2 | Rogers, Chris | I will reserve the week 21-25 November to make sure that this stuff all glues together properly. |