Actions
PC-2016-06-17-brain¶
Friday 17th June 2016
Phone details¶
http://mice.iit.edu/phonebridge.html
Guidance¶
For discussion:
- We should consider a beam test using MICE equipment
- Descope came in at 3-4 M£ and was rejected, so presumably something cheaper
- RF hardware alone is > 1 M£
- RF test (a la MTA programme) is probably not sufficiently convincing to get funding so would like a beam test
- would like to show a "lattice cell" i.e. we have control of the beam in and out of the cell (and emittance is reduced)
"Worked example":
- Consider MICE Step IV with RF replacing FC 2016-06-17_rogers_dedescope.pdf
Notes¶
Present:
Dan Kaplan
Milorad Popovic
John Cobb
Dave Neuffer
Ajit
Adam Dobbs
Paul Kyberd
Yingpeng
Victoria
Francois
Mark Tucker
- Jaroslaw has reproduced optics result on slide 3, but with solenoid mode
- Noted that if we use LiH absorber we would need new support
- Noted that there is about 20 cm extra room around the RF cavity
- Noted that one could do the energy change measurement at 3 T; then do the emittance reduction measurement at lower field (with reduced resolution measurement of energy change)
- Reacceleration
- Emittance reduction
- Operation of RF in magnetic field (w/o increasing the transverse emittance)
- Hard to achieve with existing hardware
- Note possibility to move the PRY end plate, perhaps bringing the field out onto the RF cavity
- Note vacuum issues
- Not studying coupling of cooling to RF
Victoria noted that we may not need a PRY, or may not require end plates. This may make the placement of RF easier
- Rogers asserted that one would need a movable absorber - RF
- Paul Kyberd suggested a semi-circular absorber - emittance reduction in half
Chris Rogers Noted that we can try to unlock STFC/others with reduced price tag
- Paul Soler's guidance (guess) was <~ 1 M£ cost to STFC
- There was discussion about how the cost can be reduced; take risk on RF install
- Save by reducing shut down between step iv and cooling demo
- Skimp on RF; with implicit risk
- Removing effort to redo the SSD region/civil engineering
- Reducing the schedule (and associated standing army costs)
- Let the study settle; see how the politics/money develops; then revise the analysis if it looks like it is viable
- Paul Soler requested a MC study of the cooling performance/momentum change by Monday 27th June; Rogers agreed
Updated by Rogers, Chris over 7 years ago · 7 revisions