Physics Shift Report
2
3
Start Date: 10-10-2017
4
End Date: 10-23-2017
5
Start Run: 10016
6
End Run: --
7
Physics shifter: Tanaz A. Mohayai
8
9
h2. Summary of Runs
10
11
| *Run Number*      | *Purpose*                                                                     |                               
12
| 10016        | Reference Run                                                     |
13
| 10017 - 10018       | Reference Run - Beam Bump Tuning |
14 4 Mohayai, Tanaz Angelina
| 10019 - 10077      | Empty LH2 - Flip Mode - 140MeV - 2T |
15
| 10078 -       | Empty LH2 - Flip Mode - 170MeV - 3T |
16 2 Mohayai, Tanaz Angelina
17
h2. Elog, CDB, and Reconstruction
18
19
Elog entries are ok.
20
21
CDB uploaded ok with the exception of the following runs: 
22 3 Mohayai, Tanaz Angelina
10021: it has null End Date (as reported in the corresponding elog, Run Plan GUI hung up at end of run due to illegal character in end-run comment)
23 2 Mohayai, Tanaz Angelina
10021: Start comment is wrong and should be 4 mm (not 3 mm)
24
10022: Start comment is wrong and should be 4 mm (not 3 mm)
25
26