2017-10-19 2017-10-23 physics-shifter » History » Version 16

Mohayai, Tanaz Angelina, 24 October 2017 14:51

1 1 Mohayai, Tanaz Angelina
Physics Shift Report
2
3
Start Date: 10-10-2017
4
End Date: 10-23-2017
5
Start Run: 10016
6 8 Mohayai, Tanaz Angelina
End Run: 10085
7 1 Mohayai, Tanaz Angelina
Physics shifter: Tanaz A. Mohayai
8
9
h2. Summary of Runs
10
11 15 Mohayai, Tanaz Angelina
| *Run Number*      | *Run Type* | *Absorber* | *Momentum* | *Cooling Channel Magnets* |                                
12
| 10016        | Reference Run  | Empty LH2 |  140MeV  |   Flip Mode - 2T                                              |
13
| 10017 - 10018       | Reference Run - Beam Bump Tuning  | Empty LH2 |  140MeV  |   Flip Mode - 2T                                              |
14
| 10019 - 10054      | Special Run | Empty LH2 |  140MeV  |   Flip Mode - 2T                                              |
15 16 Mohayai, Tanaz Angelina
| 10055 - 10062      | Special Run - Tracker Timing Scan | Empty LH2 |  140MeV  |   Flip Mode - 2T                                              |
16 15 Mohayai, Tanaz Angelina
| 10063 - 10077      | Special Run | Empty LH2 |  140MeV  |   Flip Mode - 2T                                              |
17 16 Mohayai, Tanaz Angelina
| 10078 - 10085      | Special Run  | Empty LH2 |  170MeV  |   Flip Mode - 3T                                              |
18 2 Mohayai, Tanaz Angelina
19
h2. Elog, CDB, and Reconstruction
20
21
Elog entries are ok.
22
23
CDB uploaded ok with the exception of the following runs: 
24 3 Mohayai, Tanaz Angelina
10021: it has null End Date (as reported in the corresponding elog, Run Plan GUI hung up at end of run due to illegal character in end-run comment)
25 2 Mohayai, Tanaz Angelina
10021: Start comment is wrong and should be 4 mm (not 3 mm)
26 1 Mohayai, Tanaz Angelina
10022: Start comment is wrong and should be 4 mm (not 3 mm)
27 6 Mohayai, Tanaz Angelina
10083: not in the CDB but properly explained in the corresponding MICE log (an attempt to start a Reference run was made but was never properly recorded in CDB)
28 2 Mohayai, Tanaz Angelina
29 1 Mohayai, Tanaz Angelina
Online reconstruction is ok
30 6 Mohayai, Tanaz Angelina
All runs are reconstructing ok with the exception of the following: 
31
10083: was never recorded in CDB (please see above for explanation)
32
33
h3. Timing Study
34 7 Mohayai, Tanaz Angelina
35 11 Mohayai, Tanaz Angelina
There were tracker timing studies carried out during this physics shift period. The corresponding run numbers are in Summary of Runs table above.
36 13 Mohayai, Tanaz Angelina
It was concluded that the baseline time (the current time) setting for the H40a task in the current run plan (3-140+M3-Test3 beamline tag in https://micewww.pp.rl.ac.uk/projects/operations/wiki/RunPlan20171015) is the optimum. This is because the "the maximum of the accepted trigger fraction is found at this baseline time". See the plot attached to elog entry: https://micewww.pp.rl.ac.uk/elog/Shift+summary/429 
37 14 Mohayai, Tanaz Angelina
38
h2. Analysis
39
40
Some runs seem to have missing spills (10022 - 10038). It may be because ISIS beam had periods of instabilities during these runs. Also, these runs had to be taken with target depth of around 34/35 mm.