Feature #1396
DAQ test plan for April
0%
Description
1. Tests of the DAQ readout through pulsar trigger. Duration: 2 days. To be done at least 1 week before the tests with beam.
2. Debugging with beam, starting with low intensity (20 - 30 triggers per spill) beams. Duration: 1 day.
3. Debugging with hight intensity beam (~ 300 triggers per spill or more if possible). Duration: 1 day.
4. TOF Calibration data taking (electron beam, ~100 triggers per spill). Duration: 2 days.
Updated by Rogers, Chris almost 10 years ago
Is this the test plan for double dip rate? or for trigger migration?
Updated by Karadzhov, Yordan almost 10 years ago
I think we can do both. Points 1-3 are necessary for both, while point 4 is relevant only for the trigger migration.
Updated by Rogers, Chris almost 10 years ago
Great. Not quite sure what you are documenting in this issue tracker, but as far as the trigger migration goes, I would want something like:
- Description of the new system
- Installation plan - what gets installed where, which racks are used
- Test plan - what tests specifically do you intend to run; which areas of the trigger system do the tests cover; are there any missing tests (e.g. things that are too tricky or require data)
- Run plan - more detail than you have above - what rate, what magnet currents, etc.
- Rollback plan - what happens if it all goes wrong
- Schedule and dates
One could pick out a subset of these items for the "doubling dip rate" activity. Then I think we need an installation review before any hardware changes are made.